Permit: T19CM03352

Parcel: 141390230


Addresses:

9300 E VALENCIA RD

Inspection Status: Approved

Inspection History: SITE - SEWER

Date Description Inspector Results Comments
03/17/2020 SITE - SEWER Approved Man holes tested and Inspected.
10/10/2019 SITE - SEWER Cancelled Canceled on site by Scott.
10/09/2019 SITE - SEWER Cancelled canceled on-site by contractor.
10/04/2019 SITE - SEWER Partial Approval Manhole #16 HCS to building #11 ok. HCS between MH#14-#15 to building #11 ok.
10/03/2019 SITE - SEWER Partial Approval HCS lines for maintenance, building #12, & #13.
10/02/2019 SITE - SEWER Partial Approval Manhole #17-18-19-20 ok to backfill.
09/27/2019 SITE - SEWER Partial Approval no inspection was done at this time due to weather conditions.
09/26/2019 SITE - SEWER Partial Approval Manhole #15 to Manhole #16 ok,
09/25/2019 SITE - SEWER Partial Approval no inspection done today due to weather conditions.
09/24/2019 SITE - SEWER Partial Approval no inspection today due to weather.
09/20/2019 SITE - SEWER Partial Approval Manhole #13 to Manhole #14, Manhole #14 to Manhole #15 ok to backfill.
09/16/2019 SITE - SEWER Partial Approval Manhole #12 to Manhole #13 ok.
09/13/2019 SITE - SEWER Partial Approval No work inspected today. Contractor cancelled upon arrival.
09/12/2019 SITE - SEWER Partial Approval Manhole 2 to 10 to 12 ok.
09/11/2019 SITE - SEWER Partial Approval Main sewer from my 2 to 10 and water main east 220’ ok
09/09/2019 SITE - SEWER Partial Approval 6" Sewer Line and tracer for Sewer discharge on building #1, #2, #3 & #14 from main sewer line ok to backfill. Per previous inspection request, all Sewer Line branch fittings have been pitched at a 45 degree angle, and flow of direction is confirmed.
09/06/2019 SITE - SEWER Partial Approval Walked site, Unable to determine direction of flow at bell fittings, branch fittings not at 45° as indicated on plans.
09/05/2019 SITE - SEWER Partial Approval 8" Sewer Line and tracer from Manhole #8 to Manhole #9 ok to backfill.
09/04/2019 SITE - SEWER Partial Approval 8" Sewer Line and tracer from Manhole #5 to Manhole #6. Manhole #6 to Manhole #7. Manhole #7 to Manhole #8. Ok to backfill.
09/03/2019 SITE - SEWER Partial Approval 8" Sewer Line and tracer from Manhole #4 to Manhole #5 ok to backfill.
08/30/2019 SITE - SEWER Partial Approval Continuation of 8" Sewer Line and tracer from Manhole #3 to Manhole #4 ok.
08/29/2019 SITE - SEWER Partial Approval 8" waste line and tracer from Manhole #2 to Man hole #3 and 20’ to Manhole #4 ok to backfill.
08/28/2019 SITE - SEWER Partial Approval 8" Sewer Line & Tracer wire from a Manhole #1 to Manhole #2 (125’) ok to backfill.