Permit: T19CM01996

Parcel: 12310001H


Addresses:

1625 N CAMPBELL AV

Inspection Status: Passed

Inspection History: COT - HCPL - Plumbing Intermediate 

Date Description Inspector Results Comments
03/05/2020 COT - HCPL - Plumbing Intermediate  JBURGE Approved Entered by DMERANZ1 - AP PER 3090 AP
02/28/2020 COT - HCPL - Plumbing Intermediate  JBURGE Partial Approval Entered by DMERANZ1 - Level #2 Residents Lounge piping for ice machine and new hand sink in Doctors Lounge area.
11/06/2019 COT - HCPL - Plumbing Intermediate  JBURGE Partial Approval Entered by DMERANZ1 - Phase IIIa, rooms 22103; 22103A, 22103B. Ok to cover progress areas.
11/01/2019 COT - HCPL - Plumbing Intermediate  JBURGE Partial Approval Entered by DMERANZ1 - In wall plumbing, corridor #22185
10/21/2019 COT - HCPL - Plumbing Intermediate  JBURGE Partial Approval Entered by DMERANZ1 - Domestic water line (1 1/2") in room 564. Ok to insulate line.
10/10/2019 COT - HCPL - Plumbing Intermediate  JBURGE Partial Approval Entered by DMERANZ1 - Meter connect to existing gas line. Pleas contact Gordon for location: 1-480-689-2148. Request has not been called in to SW Gas, could not reach after hours line.
10/09/2019 COT - HCPL - Plumbing Intermediate  JBURGE Partial Approval Entered by DMERANZ1 - Medical gas lines.
10/07/2019 COT - HCPL - Plumbing Intermediate  JCLAXTON Not ready for Inspection Entered by DMERANZ1 -
09/30/2019 COT - HCPL - Plumbing Intermediate  JBURGE Partial Approval Entered by DMERANZ1 - Phase III, Administration area, waste and vent lines (2 1/2" - 4" lines): floor drains (4 each); floor sinks, floor showers; men’s and women’s locker room restrooms.
08/22/2019 COT - HCPL - Plumbing Intermediate  JBURGE Partial Approval Entered by DMERANZ1 - Administration area North restrooms, #24548 and 24549: waste and vent lines (2"-4")
08/14/2019 COT - HCPL - Plumbing Intermediate  JBURGE Partial Approval Entered by DMERANZ1 - Level #4 restroom, patient area. Admin area, Rooms #534-537; waste and vent lines: 1 1/2"-4" lines.
07/31/2019 COT - HCPL - Plumbing Intermediate  JBURGE Partial Approval Entered by DMERANZ1 - Administration area (Phase II); waste lines upgrade at 2"-5". Dialysis area, 6 patient rooms, 2 nurse stations, 1 restroom.
07/26/2019 COT - HCPL - Plumbing Intermediate  JBURGE Partial Approval Entered by VFLORES1 - Administration area (phase 2) reroute of water and waste lines: 1 1/2 "domestic water line; 4"& 5"waste lines.
07/16/2019 COT - HCPL - Plumbing Intermediate  JBURGE Partial Approval Entered by DMERANZ1 - Domestic water (hot and cold) in rooms #44736, 44737, 44737B.
07/16/2019 COT - HCPL - Plumbing Intermediate  JBURGE Partial Approval Entered by DMERANZ1 - Domestic water (hot and cold) in rooms #44736, 44737, 44737B.
06/26/2019 COT - HCPL - Plumbing Intermediate  JBURGE Partial Approval Entered by DMERANZ1 - Rooms 22106; 22225