Permit: T19CM01996

Parcel: 12310001H


Addresses:

1625 N CAMPBELL AV


Inspection Status: Passed

Inspection History: COT - HCBU - Framing

Permit Number - T19CM01996

Inspection Description - COT - HCBU - Framing

Inspection Status - Passed

Date Description Inspector Results Comments
04/13/2020 COT - HCBU - Framing JBURGE Approved Entered by RSALDAT1 -
11/01/2019 COT - HCBU - Framing JBURGE Partial Approval Entered by DMERANZ1 - Corridor walls, Dialysis corridor #22185. Ok to insulate and cover.
10/21/2019 COT - HCBU - Framing JBURGE Partial Approval Entered by DMERANZ1 - Rooms #564; 565; adjacent corridor; 572; 730; 731; 732; 733. Ok to cover walls.
10/07/2019 COT - HCBU - Framing JCLAXTON Partial Approval Entered by DMERANZ1 - PHASE 1 CEO24507 room. PHASE 2 Physician lounge 2 walls. Corridor 23748 East and west walls. EVS room.
09/27/2019 COT - HCBU - Framing JBURGE Partial Approval Entered by DMERANZ1 - Administration rooms #24514-24515. Ok to insulate and cover.
09/13/2019 COT - HCBU - Framing JBURGE Partial Approval Entered by DMERANZ1 - Rooms hard lids. 534,535,536
09/06/2019 COT - HCBU - Framing JBURGE Partial Approval Entered by DMERANZ1 - Hard lids for restrooms at GL: 33. Ok to cover ceilings.
08/30/2019 COT - HCBU - Framing JBURGE Partial Approval Entered by DMERANZ1 - Administration area, rooms and corridors in Phase II area. Ok to insulate and Sheetrock walls.
08/29/2019 COT - HCBU - Framing JBURGE Partial Approval Entered by DMERANZ1 - Administration area Phase II; rooms and corridors.
08/28/2019 COT - HCBU - Framing JBURGE Partial Approval Entered by DMERANZ1 - Administration area offices and corridors at GL: 32-33. Ok to insulate and Sheetrock.
08/27/2019 COT - HCBU - Framing JBURGE Partial Approval Entered by DMERANZ1 - Administration area electric rooms: 507; 522; 523; 539. Ok to Sheetrock and tape progress areas
08/21/2019 COT - HCBU - Framing JBURGE Partial Approval Entered by DMERANZ1 - Administration area, rooms and corridors at GL: 2B.8-2K/26-32. Ok to one side Sheetrock in progress areas.
08/14/2019 COT - HCBU - Framing JBURGE Partial Approval Entered by DMERANZ1 - Patient restroom, Level #4.
08/01/2019 COT - HCBU - Framing JBURGE Partial Approval Entered by DMERANZ1 - Dialysis rooms (#1-#6); 2 Nurses stations, restroom
07/16/2019 COT - HCBU - Framing JBURGE Partial Approval Entered by DMERANZ1 - Framing in rooms #44736, 44737, 44737B. Ok to cover walls.
07/16/2019 COT - HCBU - Framing JBURGE Partial Approval Entered by DMERANZ1 - Framing in rooms #44736, 44737, 44737B. Ok to cover walls.
06/26/2019 COT - HCBU - Framing JBURGE Partial Approval Entered by DMERANZ1 - Phase 1A, Rooms 22106; 22225; corridor 22185. Ok to insulate and Sheetrock.