Inspection Status: Passed
Inspection History: COT - HCBU - Framing
| Date |
Description |
Inspector |
Results |
Comments |
| 04/13/2020 |
COT - HCBU - Framing |
JBURGE |
Approved |
Entered by RSALDAT1 - |
| 11/01/2019 |
COT - HCBU - Framing |
JBURGE |
Partial Approval |
Entered by DMERANZ1 - Corridor walls, Dialysis corridor #22185. Ok to insulate and cover. |
| 10/21/2019 |
COT - HCBU - Framing |
JBURGE |
Partial Approval |
Entered by DMERANZ1 - Rooms #564; 565; adjacent corridor; 572; 730; 731; 732; 733. Ok to cover walls. |
| 10/07/2019 |
COT - HCBU - Framing |
JCLAXTON |
Partial Approval |
Entered by DMERANZ1 - PHASE 1 CEO24507 room.
PHASE 2 Physician lounge 2 walls.
Corridor 23748 East and west walls.
EVS room. |
| 09/27/2019 |
COT - HCBU - Framing |
JBURGE |
Partial Approval |
Entered by DMERANZ1 - Administration rooms #24514-24515. Ok to insulate and cover. |
| 09/13/2019 |
COT - HCBU - Framing |
JBURGE |
Partial Approval |
Entered by DMERANZ1 - Rooms hard lids. 534,535,536 |
| 09/06/2019 |
COT - HCBU - Framing |
JBURGE |
Partial Approval |
Entered by DMERANZ1 - Hard lids for restrooms at GL: 33. Ok to cover ceilings. |
| 08/30/2019 |
COT - HCBU - Framing |
JBURGE |
Partial Approval |
Entered by DMERANZ1 - Administration area, rooms and corridors in Phase II area. Ok to insulate and Sheetrock walls. |
| 08/29/2019 |
COT - HCBU - Framing |
JBURGE |
Partial Approval |
Entered by DMERANZ1 - Administration area Phase II; rooms and corridors. |
| 08/28/2019 |
COT - HCBU - Framing |
JBURGE |
Partial Approval |
Entered by DMERANZ1 - Administration area offices and corridors at GL: 32-33. Ok to insulate and Sheetrock. |
| 08/27/2019 |
COT - HCBU - Framing |
JBURGE |
Partial Approval |
Entered by DMERANZ1 - Administration area electric rooms: 507; 522; 523; 539. Ok to Sheetrock and tape progress areas |
| 08/21/2019 |
COT - HCBU - Framing |
JBURGE |
Partial Approval |
Entered by DMERANZ1 - Administration area, rooms and corridors at GL: 2B.8-2K/26-32.
Ok to one side Sheetrock in progress areas.
|
| 08/14/2019 |
COT - HCBU - Framing |
JBURGE |
Partial Approval |
Entered by DMERANZ1 - Patient restroom, Level #4. |
| 08/01/2019 |
COT - HCBU - Framing |
JBURGE |
Partial Approval |
Entered by DMERANZ1 - Dialysis rooms (#1-#6); 2 Nurses stations, restroom |
| 07/16/2019 |
COT - HCBU - Framing |
JBURGE |
Partial Approval |
Entered by DMERANZ1 - Framing in rooms #44736, 44737, 44737B. Ok to cover walls. |
| 07/16/2019 |
COT - HCBU - Framing |
JBURGE |
Partial Approval |
Entered by DMERANZ1 - Framing in rooms #44736, 44737, 44737B. Ok to cover walls. |
| 06/26/2019 |
COT - HCBU - Framing |
JBURGE |
Partial Approval |
Entered by DMERANZ1 - Phase 1A, Rooms 22106; 22225; corridor 22185. Ok to insulate and Sheetrock. |