Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you cannot find what you are looking for please submit a records request.

PRO is currently experiencing an outage. Some documents and records may not be available on PRO momentarily. We apologize for the inconvenience and are working to restore full access.

Permit: T19CM01996

Parcel: 12310001H


Addresses:

1625 N CAMPBELL AV

Inspection Status: Passed

Inspection History: COT - HCBU - Framing

Date Description Inspector Results Comments
04/13/2020 COT - HCBU - Framing JBURGE Approved Entered by RSALDAT1 -
11/01/2019 COT - HCBU - Framing JBURGE Partial Approval Entered by DMERANZ1 - Corridor walls, Dialysis corridor #22185. Ok to insulate and cover.
10/21/2019 COT - HCBU - Framing JBURGE Partial Approval Entered by DMERANZ1 - Rooms #564; 565; adjacent corridor; 572; 730; 731; 732; 733. Ok to cover walls.
10/07/2019 COT - HCBU - Framing JCLAXTON Partial Approval Entered by DMERANZ1 - PHASE 1 CEO24507 room. PHASE 2 Physician lounge 2 walls. Corridor 23748 East and west walls. EVS room.
09/27/2019 COT - HCBU - Framing JBURGE Partial Approval Entered by DMERANZ1 - Administration rooms #24514-24515. Ok to insulate and cover.
09/13/2019 COT - HCBU - Framing JBURGE Partial Approval Entered by DMERANZ1 - Rooms hard lids. 534,535,536
09/06/2019 COT - HCBU - Framing JBURGE Partial Approval Entered by DMERANZ1 - Hard lids for restrooms at GL: 33. Ok to cover ceilings.
08/30/2019 COT - HCBU - Framing JBURGE Partial Approval Entered by DMERANZ1 - Administration area, rooms and corridors in Phase II area. Ok to insulate and Sheetrock walls.
08/29/2019 COT - HCBU - Framing JBURGE Partial Approval Entered by DMERANZ1 - Administration area Phase II; rooms and corridors.
08/28/2019 COT - HCBU - Framing JBURGE Partial Approval Entered by DMERANZ1 - Administration area offices and corridors at GL: 32-33. Ok to insulate and Sheetrock.
08/27/2019 COT - HCBU - Framing JBURGE Partial Approval Entered by DMERANZ1 - Administration area electric rooms: 507; 522; 523; 539. Ok to Sheetrock and tape progress areas
08/21/2019 COT - HCBU - Framing JBURGE Partial Approval Entered by DMERANZ1 - Administration area, rooms and corridors at GL: 2B.8-2K/26-32. Ok to one side Sheetrock in progress areas.
08/14/2019 COT - HCBU - Framing JBURGE Partial Approval Entered by DMERANZ1 - Patient restroom, Level #4.
08/01/2019 COT - HCBU - Framing JBURGE Partial Approval Entered by DMERANZ1 - Dialysis rooms (#1-#6); 2 Nurses stations, restroom
07/16/2019 COT - HCBU - Framing JBURGE Partial Approval Entered by DMERANZ1 - Framing in rooms #44736, 44737, 44737B. Ok to cover walls.
07/16/2019 COT - HCBU - Framing JBURGE Partial Approval Entered by DMERANZ1 - Framing in rooms #44736, 44737, 44737B. Ok to cover walls.
06/26/2019 COT - HCBU - Framing JBURGE Partial Approval Entered by DMERANZ1 - Phase 1A, Rooms 22106; 22225; corridor 22185. Ok to insulate and Sheetrock.