Inspection Status: Passed
Inspection History: COT - FCON - Fire - Final
| Date |
Description |
Inspector |
Results |
Comments |
| 05/05/2020 |
COT - FCON - Fire - Final |
CBASALDUA |
Approved |
Entered by CBASALD1 - |
| 12/17/2019 |
COT - FCON - Fire - Final |
CBASALDUA |
Partial Approval |
Entered by CBASALD1 - 1. Ok for C of O for Phase 1B Dialysis area.
2. Ok for C of O for Phase 3 Dialysis area. |
| 10/25/2019 |
COT - FCON - Fire - Final |
gsereno1 |
Partial Approval |
Entered by GSERENO1 - Okay for TCO to get ADHS inspection.
Partial for 2nd floor phase 1B dialysis minus Acid area which shall be sealed off.
Prior to Occupancy:
- Shall remove caps and place escucheons prior to occupancy
- Extinguishers shall be mounted.
- 2 smoke detectors in hall shall be retested to read corridor near room 2025 and 2026. |
| 09/04/2019 |
COT - FCON - Fire - Final |
CBASALDUA |
Partial Approval |
Entered by CBASALD1 - 1. Partial Approval for 4th Floor Tower 3 NW Observation Area. |