| 04/13/2020 |
COT - HCBU - Building Final |
JBURGE |
Approved |
Entered by RSALDAT1 - Please close out this permit.
|
| 01/23/2020 |
COT - HCBU - Building Final |
JBURGE |
Partial Approval |
Entered by DMERANZ1 - Phase 3 is complete. Ok to occupy. |
| 12/17/2019 |
COT - HCBU - Building Final |
JBURGE |
Partial Approval |
Entered by DMERANZ1 - Dialysis Phase 1 and Phase 3 are complete. Ok to occupy areas #1 & #3 |
| 12/05/2019 |
COT - HCBU - Building Final |
JBURGE |
Partial Approval |
Entered by DMERANZ1 - Phase I and Phase 2 complete. Ok to make application for Temporary Certificate of Occupancy for occupation of Administration areas (Phase 1 and Phase2). |
| 10/25/2019 |
COT - HCBU - Building Final |
JCLAXTON |
Denied |
Entered by DMERANZ1 - Dialysis area.
Missing sewer cap, access panel-bathrooms.
Backflow not tested, no drain funnel, pipe not soldered in R.O rooms
Exposed electric in lab. |
| 09/10/2019 |
COT - HCBU - Building Final |
JBURGE |
Not ready for Inspection |
Entered by DMERANZ1 - Information only. Level 2 tower 3. Endoscopy corridor above ceiling. Phase 1A, dialysis corridor. Check for occupancy. |
| 09/05/2019 |
COT - HCBU - Building Final |
JBURGE |
Partial Approval |
Entered by DMERANZ1 - Observation area,staff restrooms (2), patient restroom. Ok to occupy progress areas in order to qualify for certification. |