Inspection History Details
Inspection Status: Approved
Inspection History: ELECTRIC - RECONNECT
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 05/11/2019 | ELECTRIC - RECONNECT | Approved | (DGL) 125KVA Transformer to 1200AMP CT Cabinet. CT Cabinet to 400 AMP Utility Disconnect. Disconnect to Interconnection of Existing 1200AMP SES. 3/0 Parallel Conductors, 2-2" Conduits, #4 Neutral/ #4 Ground. Third party on site to Re-certify Gear. TEP Verbal Clearance sent at 11:30AM (DGL) |