Inspection Status: Continued
Inspection History: TDOT-EXCAV GENERAL INSPECTION
Permit Number - T18RW04938
Inspection Description - TDOT-EXCAV GENERAL INSPECTION
Inspection Status - Continued
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
08/21/2020 | TDOT-EXCAV GENERAL INSPECTION | Continued | fencing and barricades up per plan | |
01/09/2020 | TDOT-EXCAV GENERAL INSPECTION | Continued | Fencing still up per plan | |
12/17/2019 | TDOT-EXCAV GENERAL INSPECTION | Continued | Fencing up per plan. had a big meeting on site with Lance, Gloria, Adan, David and Nick from Tofel on how to handle complaints. Some thoughts were kicked around and waiting on answers from Lance and Gloria about temp crosswalks. No desicions made on site. | |
11/18/2019 | TDOT-EXCAV GENERAL INSPECTION | Continued | Fence still up per plan | |
10/29/2019 | TDOT-EXCAV GENERAL INSPECTION | Continued | Fencing still up per plan | |
10/02/2019 | TDOT-EXCAV GENERAL INSPECTION | Continued | fencing still in place per plan | |
09/11/2019 | TDOT-EXCAV GENERAL INSPECTION | Continued | fence still up per plan | |
09/04/2019 | TDOT-EXCAV GENERAL INSPECTION | Continued | fence still up per plan | |
08/15/2019 | TDOT-EXCAV GENERAL INSPECTION | Continued | fence up per plan | |
08/08/2019 | TDOT-EXCAV GENERAL INSPECTION | Continued | Fence still up for building construction---Electric conduit being installed on South side of Broadway. Bus stop has been moved and shelters returned to suntran. No complaints but area is tight.electric work should be finished by next week | |
07/24/2019 | TDOT-EXCAV GENERAL INSPECTION | Continued | fence still up no issues | |
01/16/2019 | TDOT-EXCAV GENERAL INSPECTION | Continued | Fence and closure up per plan | |
01/04/2019 | TDOT-EXCAV GENERAL INSPECTION | Continued | went out and informed toffel that mike would now be there inspector - CN | |
12/27/2018 | TDOT-EXCAV GENERAL INSPECTION | Continued | asked them to fix some traffic control - CN | |
12/20/2018 | TDOT-EXCAV GENERAL INSPECTION | Continued | had meeting down town with contractor, pdsd , matt , lance, gloria and myself - we went over expectations for the city - CN | |
12/19/2018 | TDOT-EXCAV GENERAL INSPECTION | Continued | contractor moved barricade and fence line west about 2ft per down towns direction - CN | |
12/18/2018 | TDOT-EXCAV GENERAL INSPECTION | Continued | meet with toffel about moving the fence line back 2ft on church as they had discussed at a meeting down town last friday - Joe said that he would get it taken care of today - CN | |
12/14/2018 | TDOT-EXCAV GENERAL INSPECTION | Continued | pre-con - talked about work to be done on broadway with the sewer and storm drain tie in - CN | |
11/19/2018 | TDOT-EXCAV GENERAL INSPECTION | Continued | fence up per plan - CN |