Permit: T18RW04938

Parcel: 11720016G


Addresses:

110 S CHURCH AV


Inspection Status: Continued

Inspection History: TDOT-EXCAV GENERAL INSPECTION

Permit Number - T18RW04938

Inspection Description - TDOT-EXCAV GENERAL INSPECTION

Inspection Status - Continued

Date Description Inspector Results Comments
08/21/2020 TDOT-EXCAV GENERAL INSPECTION Continued fencing and barricades up per plan
01/09/2020 TDOT-EXCAV GENERAL INSPECTION Continued Fencing still up per plan
12/17/2019 TDOT-EXCAV GENERAL INSPECTION Continued Fencing up per plan. had a big meeting on site with Lance, Gloria, Adan, David and Nick from Tofel on how to handle complaints. Some thoughts were kicked around and waiting on answers from Lance and Gloria about temp crosswalks. No desicions made on site.
11/18/2019 TDOT-EXCAV GENERAL INSPECTION Continued Fence still up per plan
10/29/2019 TDOT-EXCAV GENERAL INSPECTION Continued Fencing still up per plan
10/02/2019 TDOT-EXCAV GENERAL INSPECTION Continued fencing still in place per plan
09/11/2019 TDOT-EXCAV GENERAL INSPECTION Continued fence still up per plan
09/04/2019 TDOT-EXCAV GENERAL INSPECTION Continued fence still up per plan
08/15/2019 TDOT-EXCAV GENERAL INSPECTION Continued fence up per plan
08/08/2019 TDOT-EXCAV GENERAL INSPECTION Continued Fence still up for building construction---Electric conduit being installed on South side of Broadway. Bus stop has been moved and shelters returned to suntran. No complaints but area is tight.electric work should be finished by next week
07/24/2019 TDOT-EXCAV GENERAL INSPECTION Continued fence still up no issues
01/16/2019 TDOT-EXCAV GENERAL INSPECTION Continued Fence and closure up per plan
01/04/2019 TDOT-EXCAV GENERAL INSPECTION Continued went out and informed toffel that mike would now be there inspector - CN
12/27/2018 TDOT-EXCAV GENERAL INSPECTION Continued asked them to fix some traffic control - CN
12/20/2018 TDOT-EXCAV GENERAL INSPECTION Continued had meeting down town with contractor, pdsd , matt , lance, gloria and myself - we went over expectations for the city - CN
12/19/2018 TDOT-EXCAV GENERAL INSPECTION Continued contractor moved barricade and fence line west about 2ft per down towns direction - CN
12/18/2018 TDOT-EXCAV GENERAL INSPECTION Continued meet with toffel about moving the fence line back 2ft on church as they had discussed at a meeting down town last friday - Joe said that he would get it taken care of today - CN
12/14/2018 TDOT-EXCAV GENERAL INSPECTION Continued pre-con - talked about work to be done on broadway with the sewer and storm drain tie in - CN
11/19/2018 TDOT-EXCAV GENERAL INSPECTION Continued fence up per plan - CN