| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 02/27/2019 | TDOT-EXCAV GENERAL INSPECTION | Not ready for Inspection | NO WORK VISABLE AT THIS LOCATION | |
| 12/21/2018 | TDOT-EXCAV GENERAL INSPECTION | Approved | NO WORK VISABLE AT THIS LOCATION | |
| 09/28/2018 | TDOT-EXCAV GENERAL INSPECTION | Approved | WORK HAS BEEN COMPLETED TEP INSTALLED NEW ELECTRIC BOX ON EASTSIDE OF HOUGHTON BORED UNDER HOUGHTON TO WEST SIDE TO POLE. NO ISSUES AT THIS TIME |
|
| 08/29/2018 | TDOT-EXCAV GENERAL INSPECTION | Not ready for Inspection | CONTRACTOR NOT ON SITE | |
| 08/21/2018 | TDOT-EXCAV GENERAL INSPECTION | Not ready for Inspection | NO WORK VISABLE AT THIS LOCATION | |
| 07/30/2018 | TDOT-EXCAV GENERAL INSPECTION | Not ready for Inspection | CONTRACTOR NOT ON SITE | |
| 06/19/2018 | TDOT-EXCAV GENERAL INSPECTION | Continued | CONTRACTOR ON SITE | |
| 06/12/2018 | TDOT-EXCAV GENERAL INSPECTION | Continued | CONTRACTOR ON SITE | |
| 06/05/2018 | TDOT-EXCAV GENERAL INSPECTION | Continued | TEP CONTRACTOR IS ON SITE. HAVE A PLATE IN THE NORTHBOUND BIKE LANE. | |
| 05/31/2018 | TDOT-EXCAV GENERAL INSPECTION | Continued | TEP CONTRACTOR ON SITE. BORING UNDER HOUGHTON | |
| 05/30/2018 | TDOT-EXCAV GENERAL INSPECTION | Continued | CONTRACTOR ON SITE. BOTH SIDES OF HOUGHTON. BORING UNDER ROAD | |
| 05/25/2018 | TDOT-EXCAV GENERAL INSPECTION | Not ready for Inspection | MET WITH CONTRACTOR YESTERDAY GOING UNDER HOUGHTON FOR NEW POWER UPGRADE. |