Inspection Status: Approved
Inspection History: TDOT-EXCAV GENERAL INSPECTION
| Date |
Description |
Inspector |
Results |
Comments |
| 04/11/2018 |
TDOT-EXCAV GENERAL INSPECTION |
|
Approved |
checked asphalt work - close permit |
| 04/04/2018 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
went out and watched them prep for paving and talked about the speed hump they will be installing - CN |
| 03/26/2018 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
went and checked some of the sidewalk/ramp areas that didnt pass last time, they repoured them and they are now good, the foreman said that they would be paving april 4th and i let him know that it was past his permit date and to make sure that his permit was current while working- CN |
| 03/15/2018 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
- had meeting with pete and contractor to discuss the concrete items that had been poured and the few parts that were out of spec- CN |
| 03/14/2018 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
went out and they had just poured the old style of ramps so i looked at the plans with the contractor and showed him that they should be using the new style of ramps as the design firm stated to use. the design firm also calculated the ramps elevation to the old design standards. i told the contractor that pete and i would be out in the morning to have a meeting with them about the issue. - CN |