Inspection Status: Approved
Inspection History: TDOT-EXCAV GENERAL INSPECTION
| Date |
Description |
Inspector |
Results |
Comments |
| 03/21/2018 |
TDOT-EXCAV GENERAL INSPECTION |
|
Approved |
Work complete. No Issues. |
| 03/02/2018 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
Visit to check patches on sewer work. MH#1 still needs concrete collar. |
| 02/26/2018 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
MIdwest Contracting excavating for sewer tap on Tyndall, West side of new Building site. Patches complete on 10th St. New collar still needed on Manhole #1. |
| 02/26/2018 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
Will plate excavation overnight. Stab pipe into manhole and slurry tomorrow, then final pave on Wednesday. |
| 02/14/2018 |
TDOT-EXCAV GENERAL INSPECTION |
|
Continued |
Reminded contractor of rain in the forecast and need to clean up excess dirt, wattle stockpiles, and implenent BMP's for Park, 10th and Tyndall roadways. |