Inspection Status: Approved
Inspection History: FIRE SPKLR - OH PIPING & HYDRO
| Date |
Description |
Inspector |
Results |
Comments |
| 09/11/2019 |
FIRE SPKLR - OH PIPING & HYDRO |
|
Approved |
|
| 04/25/2019 |
FIRE SPKLR - OH PIPING & HYDRO |
|
Partial Approval |
4th floor hydro done. Shall provide evidence of metal shaved free from sprinkler piping in 408. Also duct work moved off of sprinkler head in 411. Re-inspection fee added. |
| 04/05/2019 |
FIRE SPKLR - OH PIPING & HYDRO |
|
Partial Approval |
3rd floor hydro. Re-inspection fees shall be paid prior to next inspection. |
| 03/19/2019 |
FIRE SPKLR - OH PIPING & HYDRO |
|
Partial Approval |
2nd floor and fire riser flush - pay re-inspection fees prior to calling back in |
| 03/06/2019 |
FIRE SPKLR - OH PIPING & HYDRO |
|
Partial Approval |
1st floor townhomes Upper and Lower level. |
| 02/07/2019 |
FIRE SPKLR - OH PIPING & HYDRO |
|
Partial Approval |
For the 1st floor excluding townhomes. Townhomes still need OH and hydro. Inspection 2. CB did basement. On form put AP but only PA |
| 12/17/2018 |
FIRE SPKLR - OH PIPING & HYDRO |
|
Partial Approval |
Basement Level Parking |