Inspection History Details
Inspection Status: Approved
Inspection History: FIRE SPKLR - FINAL
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 04/12/2019 | FIRE SPKLR - FINAL | Approved | ||
| 03/19/2019 | FIRE SPKLR - FINAL | Partial Approval | Everything from the list is complete. Need the fire riser room cleaned and all the ceiling tiles in place for final | |
| 01/14/2019 | FIRE SPKLR - FINAL | Partial Approval | 2nd Floor -Add 3 sprinkler heads under duct work. -Add 1 head in room 2014. |
|
| 12/19/2018 | FIRE SPKLR - FINAL | Partial Approval | fire sprinkler final for the 3rd floor for TCO Need to add one head in the janitor closet Need to add one head on the TES war room # 3094 Flow was at 59 seconds Tamper confirmed on Need to do main drain at final Place caps on the standpipes |
|
| 12/14/2018 | FIRE SPKLR - FINAL | Partial Approval | Walked floors 2 & 3. Partial Approval. Still need bell, all ceiling tiles installed and main drain test to final these floors. |