Inspection Status: Approved
Inspection History: EXCAVATION/LAYOUT REBAR & ZON
| Date |
Description |
Inspector |
Results |
Comments |
| 09/24/2019 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Approved |
|
| 08/08/2019 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Partial Approval |
E to W footing closest to south sidewalk ok to pour. |
| 05/02/2019 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Partial Approval |
Electrical platform on north side |
| 04/30/2019 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Partial Approval |
Observed South two and Northwest footings. Builder had us stamped RFI from EOR regarding UG utilities discovered during excavation for footings. Will provide stamped copy with inspection of fourth and final footing (Northeast). |