Inspection Status: Approved
Inspection History: EXCAVATION/LAYOUT REBAR & ZON
| Date |
Description |
Inspector |
Results |
Comments |
| 08/12/2019 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Approved |
Phase 5: 2 footings on south side and 4 footing on north side, ok for concrete placement |
| 08/09/2019 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Not ready for Inspection |
1- Work is incomplete |
| 07/02/2019 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Partial Approval |
phase 4, footings on L.3 from 11.5 to 13.9 (5 total) and footing at grid L.5/14.1, ok to pour. |
| 05/10/2019 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Partial Approval |
Stair tower footings and Phase 3 mezzanine footings (2 total) |
| 04/15/2019 |
EXCAVATION/LAYOUT REBAR & ZON |
|
Not ready for Inspection |
future phaseS |