Permit: T18CM08523

Parcel: 12404100A


Addresses:

930 E 2ND ST


Inspection Status: Approved

Inspection History: ENGINEERING - FINAL

Permit Number - T18CM08523

Inspection Description - ENGINEERING - FINAL

Inspection Status - Approved

Date Description Inspector Results Comments
02/16/2021 ENGINEERING - FINAL Approved
08/20/2020 ENGINEERING - FINAL Partial Approval OK FOR A TCO, BUT NOT READY FOR A FINAL. WALKED THE SITE AND HAVE ADDRESSED SOME AREAS THAT NEED TI BE ATTENDED TO PRIOR TO ALLOWING PEDESTRIAN WITHIN THE PATHWAYS. GENERAL CLEANUP OF WORK AREAS THAT HAVE BEEN WORKED ON THROUGH THE NIGHT. MINOR SWEEPING OF ALL AREAS THAT WILL BE UTILIZED FOR ACCESS INTO THE BUILDING. THE CONTRACTOR IS HAULING PLANTING MATERIAL ALONG THE EAST SIDE OF THE BUILDING BYT IS PLANNING ON HAVING IT COMPLETE BY 8:00 am THIS MORNING. ADA COMPLIANCY HAS NOT BEEN FULLY CHECKED AND WILL BE EVALUATED AND CORRECTED OVER THE NEXT FEW WEEKS AS NEEDED.
07/29/2019 ENGINEERING - FINAL Not ready for Inspection Columns need to be moved in order for forms to be set. Will reschedule for 30 July at 0700 hours.