Inspection Status: Approved
Inspection History: ELECTRIC - UNDERGROUND
| Date |
Description |
Inspector |
Results |
Comments |
| 05/20/2020 |
ELECTRIC - UNDERGROUND |
|
Approved |
|
| 06/21/2019 |
ELECTRIC - UNDERGROUND |
|
Partial Approval |
Temporary power at South perimeter wall: 3 each 4" conduits and 8 each 2" conduits. Primary power conduits from vaults to penetration of west perimeter wall; approximately 100': 30 each 4" conduits and 10 each 2" conduits. Ok to cover progress areas |
| 06/20/2019 |
ELECTRIC - UNDERGROUND |
|
Not ready for Inspection |
Penetrations in vaults from conduits need to be water proofed. |
| 06/17/2019 |
ELECTRIC - UNDERGROUND |
|
Partial Approval |
Conduits from vaults to South of perimeter wall: 28 conduits (4"), 10 stub ups at 2" outside of perimeter wall. Ok to cover progress areas. |
| 06/14/2019 |
ELECTRIC - UNDERGROUND |
|
Partial Approval |
Conduits (28 @ 4" and 10 @ 2") from South perimeter wall to 3 each electric vaults. All vault penetrations have been dry packed. |
| 02/12/2019 |
ELECTRIC - UNDERGROUND |
|
Partial Approval |
All 4 inch conduit‘s at new location for transformers and switchgear OK to cover. |