Inspection History Details
Inspection Status: Approved
Inspection History: BUILDING PRE-SLAB
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 05/20/2020 | BUILDING PRE-SLAB | Approved | ||
| 02/01/2020 | BUILDING PRE-SLAB | Partial Approval | Level #15 South: Post Tension Cable system; Ok to place concrete in progress areas. apa account to be charged for inspection $247.50 |
|
| 01/16/2020 | BUILDING PRE-SLAB | Partial Approval | 14th floor north ok to pour | |
| 01/15/2020 | BUILDING PRE-SLAB | Not ready for Inspection | (Post Tension Cable System inspection) reschedule for 16 January. | |
| 01/08/2020 | BUILDING PRE-SLAB | Partial Approval | Level #13 North, Post Tension Cable System. Ok to place concrete in progress areas. | |
| 01/02/2020 | BUILDING PRE-SLAB | Partial Approval | Level #12 South; Post Tension Cable System. Ok to place concrete. | |
| 12/30/2019 | BUILDING PRE-SLAB | Not ready for Inspection | Contractor cancelled. | |
| 12/27/2019 | BUILDING PRE-SLAB | Partial Approval | Level 12 columns northeast quadrant from core east OK to pour. Level two masonry pump room second lift OK to grout. North and west walls level two OK to grout to top of wall.Level 12 north elevator shaft OK to pour | |
| 12/03/2019 | BUILDING PRE-SLAB | Not ready for Inspection | Contractor cancelled | |
| 11/12/2019 | BUILDING PRE-SLAB | Partial Approval | Exterior sheathing on Level #2; North, East and South Exterior walls. Ok to waterproof progress areas. | |
| 11/07/2019 | BUILDING PRE-SLAB | Partial Approval | Level #8 North; Post Tension Cable System, floor slab and elevator area slab. Ok to place concrete in progress areas. | |
| 11/02/2019 | BUILDING PRE-SLAB | Partial Approval | Level #7, south portion - Post tension cable system. OK to place concrete in progress area. After hours inspection (7:00 - 9:00 am) charge APA account $165.00 for inspection services. approved by Hector |
|
| 09/20/2019 | BUILDING PRE-SLAB | Partial Approval | Post tension cable system on Level #4; GL: 1-6/A-H. Ok to place concrete in progress areas | |
| 08/17/2019 | BUILDING PRE-SLAB | Partial Approval | Level #2. Post Tension Cable system at GL: 1/A-H; H/1-7.5 ok to place concrete in progress areas After Hours Inspection at 3 hours = $247.50 Autherization to charge APA account $247.50; per signature of Ken Couturier. |
|
| 07/02/2019 | BUILDING PRE-SLAB | Partial Approval | Building pre-slab at GL: A/7-12; 12/A-H; 7/A-H; H/7-12. Ramp at GL: A/6.5-7.8; 7.8/A-B. Ok to place concrete in progress areas. | |
| 06/25/2019 | BUILDING PRE-SLAB | Partial Approval | Building slab at GL: 6.5/A-H; 1/A-H; A/1-6.5; H/1-6.5. Ok to place concrete in progress areas. |