Inspection History Details
Inspection Status: Approved
Inspection History: MECHANICAL - ABOVE CEILING
Permit Number - T18CM08138
Inspection Description - MECHANICAL - ABOVE CEILING
Inspection Status - Approved
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
07/18/2019 | MECHANICAL - ABOVE CEILING | Approved | ||
06/21/2019 | MECHANICAL - ABOVE CEILING | Not ready for Inspection | North east quadrant third-floor, unable to access area, east stairwell blocked off at second level and North stairwell blocked off at third level. OK to proceed with border tiles and some in the center area just leave enough out that I can still see into the ceiling. | |
06/20/2019 | MECHANICAL - ABOVE CEILING | Not ready for Inspection | seismic wiring not completed, lights not completed for north east quadrant third-floor. | |
06/18/2019 | MECHANICAL - ABOVE CEILING | Partial Approval | third floor center lobby OK to cover | |
06/12/2019 | MECHANICAL - ABOVE CEILING | Partial Approval | 3rd floor West. | |
06/10/2019 | MECHANICAL - ABOVE CEILING | Partial Approval | Above 3rd floor center stairway | |
06/07/2019 | MECHANICAL - ABOVE CEILING | Partial Approval | OK to cover first floor lobby west side only if work needs to get completed this weekend, otherwise would prefer to see it Monday 100% complete. Before covering finish work on lights, still being installed at time of inspection. Seismic wiring needs to be completed mainly on the far west end. Make sure mechanical branches are to there openings. One branch arm is not reaching it’s opening. Make sure mechanical dampers are accessible. | |
06/04/2019 | MECHANICAL - ABOVE CEILING | Partial Approval | third-floor southeast quadrant and men’s center restroom OK to cover. Complete last branch and diffuser at north end of that quadrant. | |
05/23/2019 | MECHANICAL - ABOVE CEILING | Partial Approval | second-floor northeast quadrant OK. Third floor OK to finish insulating low pressure system and branch ducts on west side. No new work on the east side. | |
05/08/2019 | MECHANICAL - ABOVE CEILING | Partial Approval | Southeast open area 1st floor OK | |
04/26/2019 | MECHANICAL - ABOVE CEILING | Partial Approval | Second floor north mechanical overhead Approved | |
04/23/2019 | MECHANICAL - ABOVE CEILING | Partial Approval | low pressure mains and branches on second-floor OK to finish insulating | |
04/08/2019 | MECHANICAL - ABOVE CEILING | Partial Approval | Low pressure mains in open office, and conference room on 1st floor, ok to insulate. | |
03/26/2019 | MECHANICAL - ABOVE CEILING | Partial Approval | Main duct trunks on 1 and 3 ok to insulate | |
03/25/2019 | MECHANICAL - ABOVE CEILING | Partial Approval | second floor rectangular duct OK to insulate |