Inspection History Details
Inspection Status: Approved
Inspection History: PLUMBING - ABOVE CEILING
Permit Number - T18CM08138
Inspection Description - PLUMBING - ABOVE CEILING
Inspection Status - Approved
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
07/18/2019 | PLUMBING - ABOVE CEILING | Approved | ||
06/21/2019 | PLUMBING - ABOVE CEILING | Not ready for Inspection | North east quadrant third-floor, unable to access area, east stairwell blocked off at second level and North stairwell blocked off at third level. OK to proceed with border tiles and some in the center area just leave enough out that I can still see into the ceiling. | |
06/20/2019 | PLUMBING - ABOVE CEILING | Not ready for Inspection | seismic wiring not completed, lights not completed for north east quadrant third-floor. | |
06/12/2019 | PLUMBING - ABOVE CEILING | Partial Approval | 3rd floor West. | |
06/10/2019 | PLUMBING - ABOVE CEILING | Partial Approval | Above 3rd floor center stairway | |
06/07/2019 | PLUMBING - ABOVE CEILING | Partial Approval | OK to cover first floor lobby west side only if work needs to get completed this weekend, otherwise would prefer to see it Monday 100% complete. Before covering finish work on lights, still being installed at time of inspection. Seismic wiring needs to be completed mainly on the far west end. Make sure mechanical branches are to there openings. One branch arm is not reaching it’s opening. Make sure mechanical dampers are accessible. | |
06/04/2019 | PLUMBING - ABOVE CEILING | Partial Approval | third floor south east quadrant and third-floor center restrooms OK to cover. | |
04/15/2019 | PLUMBING - ABOVE CEILING | Partial Approval | 3rd fl VTR for break room, and future. 3rd floor men’s/women’s north. Plumbing. Water supply and fixture lines at 3rd fl, under test at 100 psi. |
|
03/25/2019 | PLUMBING - ABOVE CEILING | Partial Approval | second floor OK except break room |