Permit: T18CM08138

Parcel: 132130680

Inspection Status: Approved

Inspection History: ELECTRIC - FINAL

Permit Number - T18CM08138

Inspection Description - ELECTRIC - FINAL

Inspection Status - Approved

Date Description Inspector Results Comments
09/26/2019 ELECTRIC - FINAL Approved
07/22/2019 ELECTRIC - FINAL Partial Approval missing exterior lighting for main front door entrance
07/09/2019 ELECTRIC - FINAL Partial Approval generator already looked at and is OK per previous inspector Adam.
06/26/2019 ELECTRIC - FINAL Not ready for Inspection still too much confusion with egress and exit signs for a TCO at this point. Any part of the building that is going to have a TCO needs to have exit signs within sight and directing you to a clear path of egress that exits the building and not into construction, until that time not able to approve. Also need to address the fact that the fire foam used on all the fire rated walls is not the UL listing that is on the drawings, please get an RFI confirming this is an OK substitute.
06/24/2019 ELECTRIC - FINAL Not ready for Inspection this was to walk the first and second floor for a TCO. Only walked 1st floor. Exit signs discussed from original walk still missing, Big meeting room on first floor has no exit signs to know which way to go out. East side stairwell first level, path of egress is not clear, equipment and dirt piles in the way. West side stairwell and lobby also has construction going on, path of egress not fully clear including construction equipment outside of doors. Construction barricades may need to be improved in order to maintain safety pending on how we are routing people, especially if there a TCO on only part of one floor. Drinking water will need to be provided as the chlorination report has not been submitted and approved.