Inspection Status: Approved
Inspection History: FRAMING
| Date |
Description |
Inspector |
Results |
Comments |
| 07/18/2019 |
FRAMING |
|
Approved |
|
| 06/04/2019 |
FRAMING |
|
Partial Approval |
third floor center restrooms OK |
| 03/15/2019 |
FRAMING |
|
Partial Approval |
All 2nd floor exterior wall framing, and interior room frames ok. Stairwells and large chases not framed yet |
| 03/12/2019 |
FRAMING |
|
Partial Approval |
For fitness center, fitness center bathrooms, and kitchen |
| 02/28/2019 |
FRAMING |
|
Partial Approval |
2nd floor all exterior walls and interior walls to grid line 5 ok to 1 side |
| 02/22/2019 |
FRAMING |
|
Partial Approval |
OK to one side rock from Gridline 1 to 2 from B to G and from Gridline 1 to 11 from E to G. |
| 02/13/2019 |
FRAMING |
|
Partial Approval |
Walked with super GL E - G from 1 to 6 clean up all framing at duct work and diagonal bracing OK to one side and Recall 1035 |