Inspection Status: Not Ready
Inspection History: COT - LCPL - Rough Soil
| Date |
Description |
Inspector |
Results |
Comments |
| 10/26/2022 |
COT - LCPL - Rough Soil |
|
Not Ready |
|
| 03/02/2022 |
COT - LCPL - Rough Soil |
JBURGE |
Partial Approval |
Entered by VVERA1 - Partial. Roof drain from roof to main drainage sewer at 4” line located on Northeast section of building. Back flow lines at 1 1/2’ - 2” lines on West side of building. Ok to cover progress areas. |
| 02/02/2022 |
COT - LCPL - Rough Soil |
JBURGE |
Partial Approval |
Entered by NGARCIA3 - Partial. 4” sewer line from main sewer line to building; approximately 18 feet. Dual clean out. Ok to cover progress areas. |
| 01/07/2022 |
COT - LCPL - Rough Soil |
JBURGE |
Partial Approval |
Entered by VVERA1 - Partial. Two 4 inch waste lines from build to main sewer connection on 7th Street. Approximately 75 feet. Ok to cover progress areas. |
| 12/13/2021 |
COT - LCPL - Rough Soil |
TLUNDBERG |
Partial Approval |
Entered by RSALDAT1 - pa
Rough for 5 baths and a mop sink ok to backfill and patch concrete. Rough is complete except for connection in basement to the exterior main. |
| 08/09/2023 |
COT - LCPL - Rough Soil |
|
Passed |
|