Permit: T18CM04589

Parcel: 14043013B

Inspection Status: Approved

Inspection History: PLUMBING - PRE SLAB

Date Description Inspector Results Comments
05/30/2019 PLUMBING - PRE SLAB Approved
04/23/2019 PLUMBING - PRE SLAB Partial Approval 4" copper riser 100 psi test at south mechanical yard
12/17/2018 PLUMBING - PRE SLAB Not ready for Inspection Work not complete
12/17/2018 PLUMBING - PRE SLAB Partial Approval Area D GL G-N from 2-5
After hours APA account $165.00
12/06/2018 PLUMBING - PRE SLAB Partial Approval Area E only
11/29/2018 PLUMBING - PRE SLAB Partial Approval Areas E&F between CL. D to G
11/16/2018 PLUMBING - PRE SLAB Partial Approval AREA A only