Inspection History Details
Inspection Status: Approved
Inspection History: PLUMBING - PRE SLAB
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 05/30/2019 | PLUMBING - PRE SLAB | Approved | ||
| 04/23/2019 | PLUMBING - PRE SLAB | Partial Approval | 4" copper riser 100 psi test at south mechanical yard | |
| 12/17/2018 | PLUMBING - PRE SLAB | Not ready for Inspection | Work not complete | |
| 12/17/2018 | PLUMBING - PRE SLAB | Partial Approval | Area D GL G-N from 2-5 After hours APA account $165.00 |
|
| 12/06/2018 | PLUMBING - PRE SLAB | Partial Approval | Area E only | |
| 11/29/2018 | PLUMBING - PRE SLAB | Partial Approval | Areas E&F between CL. D to G | |
| 11/16/2018 | PLUMBING - PRE SLAB | Partial Approval | AREA A only |