Date Description Inspector Results Comments
05/16/2019 BUILDING PRE-SLAB Approved
05/14/2019 BUILDING PRE-SLAB Partial Approval Mechanical yard slab GL 0-2 from G-K only
05/06/2019 BUILDING PRE-SLAB Partial Approval Boiler and compressor Pad only
05/06/2019 BUILDING PRE-SLAB Partial Approval RO Pump pad GL H from 1-2
After hours APA account $165
04/24/2019 BUILDING PRE-SLAB Partial Approval North LN2 vaporizer pad
generator pads East equipment yard
01/25/2019 BUILDING PRE-SLAB Partial Approval Slab for canopy at east end of building OK to pour.
01/15/2019 BUILDING PRE-SLAB Partial Approval Area B & C
GL K-N from 5-11
01/02/2019 BUILDING PRE-SLAB Partial Approval After hours APA account $165.00
GL G-K from 5-9 only
12/17/2018 BUILDING PRE-SLAB Partial Approval Area D GL G-N from 2-5
After hours APA account $165.00
12/11/2018 BUILDING PRE-SLAB Partial Approval After hours APA account $165.00
Area F GL A-D from 2-6 only
12/10/2018 BUILDING PRE-SLAB Partial Approval After hours APA account $165.00
Area E GL A-D from 6-8
11/29/2018 BUILDING PRE-SLAB Partial Approval Areas E&F between CL. D to G
11/15/2018 BUILDING PRE-SLAB Not ready for Inspection Work not complete
11/15/2018 BUILDING PRE-SLAB Partial Approval After hours APA account $165
area A only