05/30/2019 | ELECTRIC - UNDERGROUND | Approved | ||
05/23/2019 | ELECTRIC - UNDERGROUND | Denied | Provide proper clearance steel from soil 4 pole bases north access road. | |
05/15/2019 | ELECTRIC - UNDERGROUND | Partial Approval | 1 1/2" conduit main feeders to pole bases south and north access rd | |
05/06/2019 | ELECTRIC - UNDERGROUND | Partial Approval | North parking lot six pole bases conduit only | |
04/15/2019 | ELECTRIC - UNDERGROUND | Partial Approval | 2 HGL & LG2 panels 2 communication boxes 2 each H100 & L 100 risers only All 4" too chillers 8 x 4" future stubs from box to building exterior west |
|
04/12/2019 | ELECTRIC - UNDERGROUND | Partial Approval | UNDERGROUND AREA G OK TO COVER | |
04/11/2019 | ELECTRIC - UNDERGROUND | Partial Approval | HMSD4A switchgear duct bank GL J/2 | |
04/08/2019 | ELECTRIC - UNDERGROUND | Partial Approval | All underground exterior of building east only | |
04/03/2019 | ELECTRIC - UNDERGROUND | Partial Approval | 2 x 5" to main gear duct bank GL 2 from H-I only | |
04/01/2019 | ELECTRIC - UNDERGROUND | Partial Approval | HMSB gear 1 & 2 | |
03/26/2019 | ELECTRIC - UNDERGROUND | Partial Approval | 2 x 5" Medium voltage across road 60 feet only | |
03/25/2019 | ELECTRIC - UNDERGROUND | Partial Approval | 4×5 inch classified duck bank east side HMS B-3 mechanical yard |
|
03/05/2019 | ELECTRIC - UNDERGROUND | Partial Approval | Fire pump feed from vault six E. to the corner of the building then north to Gridline four OK to cover. Conduit bundle between vault four and five and between five and six OK to cover |
|
02/21/2019 | ELECTRIC - UNDERGROUND | Partial Approval | Vaults 1, 2, & 3 ok to cover conduit. Medium voltage future OK to cover | |
02/20/2019 | ELECTRIC - UNDERGROUND | Cancelled | canceled and rescheduled for tomorrow | |
02/06/2019 | ELECTRIC - UNDERGROUND | Partial Approval | Duct bank south of building MV from Gridline G to I OK to pour | |
02/01/2019 | ELECTRIC - UNDERGROUND | Partial Approval | 4×5 inch duct bank west of vault 130 feet | |
01/04/2019 | ELECTRIC - UNDERGROUND | Not ready for Inspection | no work | |
12/28/2018 | ELECTRIC - UNDERGROUND | Partial Approval | column grounding grid lines 7 to 9 from G to N | |
12/27/2018 | ELECTRIC - UNDERGROUND | Not ready for Inspection | Unable to contact or leave message no work | |
12/26/2018 | ELECTRIC - UNDERGROUND | Not ready for Inspection | Work not complete enough to inspect | |
12/20/2018 | ELECTRIC - UNDERGROUND | Partial Approval | Duck bank 4×5 inch termination east of vault GL 1 | |
12/18/2018 | ELECTRIC - UNDERGROUND | Partial Approval | column grounding grid lines 7 from G to N | |
12/17/2018 | ELECTRIC - UNDERGROUND | Partial Approval | 4 x 5" west of vault GL 1 & 1 x 4" temp power |