| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 07/30/2019 | ELECTRIC - UFER | Approved | ||
| 05/23/2019 | ELECTRIC - UFER | Denied | Provide proper clearance steel from soil 4 pole bases north access road. | |
| 05/15/2019 | ELECTRIC - UFER | Partial Approval | Completion of grounding loop main building only | |
| 05/09/2019 | ELECTRIC - UFER | Partial Approval | UFER ground at structural steel southeast corner ok to cover. UFER ground for chillers OK to cover. |
|
| 05/07/2019 | ELECTRIC - UFER | Partial Approval | 6 pole bases north parking lot only | |
| 05/06/2019 | ELECTRIC - UFER | Partial Approval | completion of column grounding except two columns at West mechanical yard Completion of ground ring except tie in at south west corner of building |
|
| 04/11/2019 | ELECTRIC - UFER | Partial Approval | Grounding a tank pads between grid lines G -H on Gridline 1 Grounding at three switchgear and vaults with ground rods GL 1.5 from H-J |
|
| 04/01/2019 | ELECTRIC - UFER | Partial Approval | Ground ring at column GL 1 from G-H | |
| 03/26/2019 | ELECTRIC - UFER | Partial Approval | Ground ring GL 1 from D-E only | |
| 03/25/2019 | ELECTRIC - UFER | Partial Approval | Column line A-E GL 2 and A-C GL 1 with ground rods | |
| 02/21/2019 | ELECTRIC - UFER | Partial Approval | grid line N to K grounding ok to cover. | |
| 02/06/2019 | ELECTRIC - UFER | Partial Approval | Grounding unless side of building OK to cover | |
| 02/01/2019 | ELECTRIC - UFER | Partial Approval | Ground ring at column N/9 through L /10.5 |