Inspection History Details
Inspection Status: Approved
Inspection History: EXCAVATION/LAYOUT REBAR & ZON
Permit Number - T18CM04356
Inspection Description - EXCAVATION/LAYOUT REBAR & ZON
Inspection Status - Approved
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
05/30/2019 | EXCAVATION/LAYOUT REBAR & ZON | Approved | ||
05/13/2019 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | Mechanical pads area G OK to pour. | |
05/09/2019 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | OK TO POUR PAD AT SWITCHGEAR LOCATION | |
05/09/2019 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | slab on grade area F OK to pour. Chiller pad southwest corner OK to pour. | |
04/19/2019 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | LN2 pad with ground | |
04/12/2019 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | PIER FOOTINGS AT SOUTH DUCT BANK OK TO POUR | |
04/11/2019 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | 4 cooling tower piers per detail 107/S3.0 GL 1 from K-L | |
04/05/2019 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | Last footing for small canopy on south side of building ok to pour | |
04/02/2019 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | 3 each F-16 footers Area G small canopy. See highlighted AS2.09 page | |
03/28/2019 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | F-9 footing GL H from 1-1.8 only | |
03/26/2019 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | F-5 footings GL Z.3 from Z.B - Z.D F14 footer GL Z.A from Z.1 - Z.2 See highlighted plan |
|
03/14/2019 | EXCAVATION/LAYOUT REBAR & ZON | Not ready for Inspection | no work completed | |
03/14/2019 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | Footing anf pedestal detail Af-01 Cooling towers footings 8 each |
|
03/13/2019 | EXCAVATION/LAYOUT REBAR & ZON | Not ready for Inspection | no work | |
03/12/2019 | EXCAVATION/LAYOUT REBAR & ZON | Not ready for Inspection | no work | |
03/11/2019 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | Canopy footings F-15 footer GL Z2 from ZB-ZC F-13 column footer Z2/ZD F-14 footer GL ZE from Z.2-Z1 Column footings Z.D/Z1 & ZB/Z.1 |
|
01/07/2019 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | After hours APA account $165.00 GL G-K from 9- 10 8 mono pour in lieu of stem wall per detail 106/ s3.0 |