Inspection Status: Approved
Inspection History: PLUMBING - INTERMEDIATE
| Date |
Description |
Inspector |
Results |
Comments |
| 04/05/2019 |
PLUMBING - INTERMEDIATE |
|
Approved |
|
| 01/11/2019 |
PLUMBING - INTERMEDIATE |
|
Partial Approval |
Heated Hot water and return system; tested at 158 psi.. Ok to insulate progress areas. |
| 12/19/2018 |
PLUMBING - INTERMEDIATE |
|
Partial Approval |
4 each 4” roof drains at North entry area. Under Hydro test - ok to drain lines |
| 12/04/2018 |
PLUMBING - INTERMEDIATE |
|
Partial Approval |
Domestic and sanitary water lines. ( 2@ 3/4", 1 @ 1 1/2") overhead. All areas except for hot water closet - connections to be completed at a later date. |
| 11/26/2018 |
PLUMBING - INTERMEDIATE |
|
Partial Approval |
Roof drains (2) at North entry area. |
| 10/11/2018 |
PLUMBING - INTERMEDIATE |
|
Partial Approval |
Radiant Heating/Cooling from Manifold #3 system tested at 60 psi. Ok to cover. |
| 10/04/2018 |
PLUMBING - INTERMEDIATE |
|
Partial Approval |
Radiant Heating/Cooling; Radiant floor manifold #2; tested at 60 psi. Ok to cover progress areas. |