Inspection Status: Approved
Inspection History: PLUMBING - INTERMEDIATE
Permit Number - T18CM02149
Inspection Description - PLUMBING - INTERMEDIATE
Inspection Status - Approved
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
04/05/2019 | PLUMBING - INTERMEDIATE | Approved | ||
01/11/2019 | PLUMBING - INTERMEDIATE | Partial Approval | Heated Hot water and return system; tested at 158 psi.. Ok to insulate progress areas. | |
12/19/2018 | PLUMBING - INTERMEDIATE | Partial Approval | 4 each 4” roof drains at North entry area. Under Hydro test - ok to drain lines | |
12/04/2018 | PLUMBING - INTERMEDIATE | Partial Approval | Domestic and sanitary water lines. ( 2@ 3/4", 1 @ 1 1/2") overhead. All areas except for hot water closet - connections to be completed at a later date. | |
11/26/2018 | PLUMBING - INTERMEDIATE | Partial Approval | Roof drains (2) at North entry area. | |
10/11/2018 | PLUMBING - INTERMEDIATE | Partial Approval | Radiant Heating/Cooling from Manifold #3 system tested at 60 psi. Ok to cover. | |
10/04/2018 | PLUMBING - INTERMEDIATE | Partial Approval | Radiant Heating/Cooling; Radiant floor manifold #2; tested at 60 psi. Ok to cover progress areas. |