Inspection Status: Approved
Inspection History: PLUMBING - SEWER HCS CONNECT
| Date |
Description |
Inspector |
Results |
Comments |
| 07/15/2019 |
PLUMBING - SEWER HCS CONNECT |
|
Approved |
|
| 07/10/2019 |
PLUMBING - SEWER HCS CONNECT |
|
Not ready for Inspection |
I will need to meet with the contractor and other inspectors to ensure all work is complete. |
| 08/27/2018 |
PLUMBING - SEWER HCS CONNECT |
|
Partial Approval |
8" TAP INTO MANHOLE WITH 4" BRANCHES PARALLEL TO WEST WALL OF BLD. OK TO BACKFILL |
| 08/02/2018 |
PLUMBING - SEWER HCS CONNECT |
|
Partial Approval |
4" WASTE LINE AT GL: A/3.2 - 6; UNDER TEST. OK TO COVER PROGRESS AREAS. |
| 07/19/2018 |
PLUMBING - SEWER HCS CONNECT |
|
Not ready for Inspection |
CONTRACTOR CANCELLED. |