Inspection History Details
Inspection Status: Approved
Inspection History: EXCAVATION/LAYOUT REBAR & ZON
Permit Number - T18CM00899
Inspection Description - EXCAVATION/LAYOUT REBAR & ZON
Inspection Status - Approved
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
07/15/2019 | EXCAVATION/LAYOUT REBAR & ZON | Approved | ||
07/10/2019 | EXCAVATION/LAYOUT REBAR & ZON | Not ready for Inspection | I will need to meet with the contractor and other inspectors to ensure all work is complete. | |
10/19/2018 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | Elevator shaft from level 3 to 4 OK to pour | |
10/10/2018 | EXCAVATION/LAYOUT REBAR & ZON | Not ready for Inspection | elevator core and stairway at level two OK to pour | |
10/05/2018 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | Remainder of level 2 floor ok to pour | |
10/03/2018 | EXCAVATION/LAYOUT REBAR & ZON | Cancelled | Inspection cancled | |
09/11/2018 | EXCAVATION/LAYOUT REBAR & ZON | Denied | COLUMNS NOT READY ENOUGH TO INSPECT. WILL TRY AGAIN AT 3:00 INSPECTION. | |
09/06/2018 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | FOOTING FOR NORTH SIDE OF RAMP WALL OK TO POUR | |
09/05/2018 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | COLUMNS - GRID LINES H & J / 1.2, 2.3, 4.0, 6 & G&J ON 7 & G/1.5 ALL OK TO POUR WITH APPROVAL OF PHOTOS TO BE PROVIDED PRIOR TO POUR. | |
08/30/2018 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | CMU FOOTING GL 5.3 TO 4.5 / F TO J OK TO POUR | |
08/27/2018 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | FOOTINGS NORTHEAST AND EAST SIDES GRIDLINE 5.3 TO 3.2 / F TO G ALL OK TO POUR. | |
08/23/2018 | EXCAVATION/LAYOUT REBAR & ZON | Cancelled | ||
08/23/2018 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | EXCAVATION FOR ELECTRIC PRIMARIES FROM BEHIND 'PIOLOGY' WEST TO TYNDALL AV OK TO COVER. | |
08/17/2018 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | 5 CAISONS IN THE SOUTHWEST CORNER OF THE PROJECT WERE HELD LOW WHEN FIRST POURED. OK TO CONTINUE TO GRADE WITH APPROVAL OF SPECIAL INSPECTOR. | |
08/15/2018 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | ALL COLUMNS LEVEL1 SOUTH OK TO POUR | |
08/10/2018 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | LEVEL 1 FLOOR AND WALLS FROM BASEMENT UP TO LEVEL 1 OK TO POUR | |
08/09/2018 | EXCAVATION/LAYOUT REBAR & ZON | Cancelled | ||
08/07/2018 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | GRID LINE E TO F.2/4 TO6 BASEMENT WALLS OK TO POUR | |
08/03/2018 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | F-5 FOOTING AT GL: F.2/4.1 - 5.2; POURED 2 AUGUST 2018: CITY OF TUCSON DID NOT INSPECT FOOTING, SPECIAL INSPECTION ON 2 AUGUST 2018. | |
07/27/2018 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | GARAGE LEVEL #1, SLAB AT GL: A/4.1-7; 4.1/A - J, J/4.1-7. OK TO PLACE CONCRETE | |
07/25/2018 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | LEVEL #1, GARAGE (LOWER). ELEVATOR WALLS AT 0' - 11'. OK TO PLACE CONCRETE. | |
07/20/2018 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | BASEMENT SLAB AT GL: A-E.75/1 - 4.1. OK TO PLACE CONCRETE. | |
07/19/2018 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | SOUTH WEST AT GL: 7/A-C; OK TO PLACE CONCRETE. | |
07/18/2018 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | CALLED IN INSPECTION WAS PERFORMED ON 17 JULY 2018. | |
07/17/2018 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | COLUMNS AT GL: B/2.5 - 3.2; 6/E - G. OK TO PLACE CONCRETE | |
07/16/2018 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | BASEMENT RETAINING WALL (WEST) AT GL: A/3.2 - 4; A - B/ 3.2. OK TO PLACE CONCRETE. | |
07/12/2018 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | SOUTH BASEMENT WALL AT GL: 7/B - H.9; COLUMNS AT GL: C/5; 1.2/D, E, F. OK TO PLACE CONCRETE. | |
07/11/2018 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | WALL FOOTING AT GL: A/4.1 - 7: EAST BASEMENT WALL. COLUMNS : 4 @ GL: G/3 - 4.1 (CC2A); G/1 (CC1), E/6 (CC5.3). OK TO PLACE CONCRETE. | |
07/10/2018 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | COLUMNS AT GL: E/5, (CC4); D/6.1 (CC5): WALL FOOTINGS AT GL: 3.2/A - B.5; A/3.2 - 3.9. OK TO PLACE CONCRETE. | |
07/05/2018 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | FOOTING (F1) AT GL: 7/A - H.9, OK TO PLACE CONCRETE IN PROGRESS AREAS. | |
07/03/2018 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | FOOTING (F4) AT GL: A/3.9 - 7. OK TO PLACE CONCRETE. | |
07/02/2018 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | CAISSON FOOTING CAGES (19) AT DSF: 1, 1.4, 1.5, 1.6, 1.7, 1.8, 6.10, 6.11, 6.12, 6.8, 6.9, 5.1, 9, 9.1. CM-1 WALL AT GL: E.2-E.5/1.5-2; 1.5/E.9- F. OK TO PLACE CONCRETE IN PROGRESS AREAS. |
|
06/28/2018 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* LOWEST LEVEL OF ELEVATOR PIT WALLS OK TO POUR | |
06/27/2018 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | CAISSON FOOTING CAGES (12) TO BE SET IN FOOTINGS AT GL: A-F/6-7: B/4-5. #DSF: 1, 1.2, 1.1, 2, 4.2, 5.2, 5.3, 6, 6.5, 6.6. OK TO PLACE REBAR CAGES. | |
06/26/2018 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | STAIRWELL #1 WALL AT GL: 3.2/A-C. OK TO PLACE CONCRETE. | |
06/25/2018 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | NORTH EAST STAIR WELL FOOTING (F4) AT GL: E.5-F.2/1.3-1.5. COLUMNS (3) AT GL: D/3.2; 3.2/D; E/4. SHEAR WALL #7; STAIRWELL #2 WALLS. OK TO PLACE CONCRETE IN PROGRESS AREAS. | |
06/19/2018 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | BASE OF NORTHEAST ELEVATOR OK TO POUR | |
06/08/2018 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | EAST STAIRWELL GRADE BEAMS OK TO POUR. NORTHEAST ELEVATOR SHAFT OK TO POUR GRADE BEAMS. | |
06/07/2018 | EXCAVATION/LAYOUT REBAR & ZON | Not ready for Inspection | ||
06/06/2018 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | GRADE BEAMS AT NORTHWEST STAIRWAY OK TO POUR | |
06/01/2018 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | CAISONS IN ELEVATOR PIT TOP OFF GRADE BEAM AND FOOTING NORTH SIDE OF PIT OK TO PLACE CONCRETE |
|
05/25/2018 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | CAISONS AT GRIDLINES D & E / 2, 3.2, 4, 5 AND B & C / 2.5, 3.2, 3.5, AND C/5, C/4 ALL OK TO PLACE CONCRETE | |
05/23/2018 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | SIX CAISONS (GL E.7/2,2.2,3.1 & GL F/2,2.2,3.1) OK TO POUR |