Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you cannot find what you are looking for please submit a records request.

PRO is currently experiencing an outage. Some documents and records may not be available on PRO momentarily. We apologize for the inconvenience and are working to restore full access.

Permit: T18CM00899

Parcel: 11504498B


Addresses:

850 E SPEEDWAY BL

Inspection Status: Approved

Inspection History: EXCAVATION/LAYOUT REBAR & ZON

Date Description Inspector Results Comments
07/15/2019 EXCAVATION/LAYOUT REBAR & ZON Approved
07/10/2019 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection I will need to meet with the contractor and other inspectors to ensure all work is complete.
10/19/2018 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Elevator shaft from level 3 to 4 OK to pour
10/10/2018 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection elevator core and stairway at level two OK to pour
10/05/2018 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Remainder of level 2 floor ok to pour
10/03/2018 EXCAVATION/LAYOUT REBAR & ZON Cancelled Inspection cancled
09/11/2018 EXCAVATION/LAYOUT REBAR & ZON Denied COLUMNS NOT READY ENOUGH TO INSPECT. WILL TRY AGAIN AT 3:00 INSPECTION.
09/06/2018 EXCAVATION/LAYOUT REBAR & ZON Partial Approval FOOTING FOR NORTH SIDE OF RAMP WALL OK TO POUR
09/05/2018 EXCAVATION/LAYOUT REBAR & ZON Partial Approval COLUMNS - GRID LINES H & J / 1.2, 2.3, 4.0, 6 & G&J ON 7 & G/1.5 ALL OK TO POUR WITH APPROVAL OF PHOTOS TO BE PROVIDED PRIOR TO POUR.
08/30/2018 EXCAVATION/LAYOUT REBAR & ZON Partial Approval CMU FOOTING GL 5.3 TO 4.5 / F TO J OK TO POUR
08/27/2018 EXCAVATION/LAYOUT REBAR & ZON Partial Approval FOOTINGS NORTHEAST AND EAST SIDES GRIDLINE 5.3 TO 3.2 / F TO G ALL OK TO POUR.
08/23/2018 EXCAVATION/LAYOUT REBAR & ZON Cancelled
08/23/2018 EXCAVATION/LAYOUT REBAR & ZON Partial Approval EXCAVATION FOR ELECTRIC PRIMARIES FROM BEHIND 'PIOLOGY' WEST TO TYNDALL AV OK TO COVER.
08/17/2018 EXCAVATION/LAYOUT REBAR & ZON Partial Approval 5 CAISONS IN THE SOUTHWEST CORNER OF THE PROJECT WERE HELD LOW WHEN FIRST POURED. OK TO CONTINUE TO GRADE WITH APPROVAL OF SPECIAL INSPECTOR.
08/15/2018 EXCAVATION/LAYOUT REBAR & ZON Partial Approval ALL COLUMNS LEVEL1 SOUTH OK TO POUR
08/10/2018 EXCAVATION/LAYOUT REBAR & ZON Partial Approval LEVEL 1 FLOOR AND WALLS FROM BASEMENT UP TO LEVEL 1 OK TO POUR
08/09/2018 EXCAVATION/LAYOUT REBAR & ZON Cancelled
08/07/2018 EXCAVATION/LAYOUT REBAR & ZON Partial Approval GRID LINE E TO F.2/4 TO6 BASEMENT WALLS OK TO POUR
08/03/2018 EXCAVATION/LAYOUT REBAR & ZON Partial Approval F-5 FOOTING AT GL: F.2/4.1 - 5.2; POURED 2 AUGUST 2018: CITY OF TUCSON DID NOT INSPECT FOOTING, SPECIAL INSPECTION ON 2 AUGUST 2018.
07/27/2018 EXCAVATION/LAYOUT REBAR & ZON Partial Approval GARAGE LEVEL #1, SLAB AT GL: A/4.1-7; 4.1/A - J, J/4.1-7. OK TO PLACE CONCRETE
07/25/2018 EXCAVATION/LAYOUT REBAR & ZON Partial Approval LEVEL #1, GARAGE (LOWER). ELEVATOR WALLS AT 0' - 11'. OK TO PLACE CONCRETE.
07/20/2018 EXCAVATION/LAYOUT REBAR & ZON Partial Approval BASEMENT SLAB AT GL: A-E.75/1 - 4.1. OK TO PLACE CONCRETE.
07/19/2018 EXCAVATION/LAYOUT REBAR & ZON Partial Approval SOUTH WEST AT GL: 7/A-C; OK TO PLACE CONCRETE.
07/18/2018 EXCAVATION/LAYOUT REBAR & ZON Partial Approval CALLED IN INSPECTION WAS PERFORMED ON 17 JULY 2018.
07/17/2018 EXCAVATION/LAYOUT REBAR & ZON Partial Approval COLUMNS AT GL: B/2.5 - 3.2; 6/E - G. OK TO PLACE CONCRETE
07/16/2018 EXCAVATION/LAYOUT REBAR & ZON Partial Approval BASEMENT RETAINING WALL (WEST) AT GL: A/3.2 - 4; A - B/ 3.2. OK TO PLACE CONCRETE.
07/12/2018 EXCAVATION/LAYOUT REBAR & ZON Partial Approval SOUTH BASEMENT WALL AT GL: 7/B - H.9; COLUMNS AT GL: C/5; 1.2/D, E, F. OK TO PLACE CONCRETE.
07/11/2018 EXCAVATION/LAYOUT REBAR & ZON Partial Approval WALL FOOTING AT GL: A/4.1 - 7: EAST BASEMENT WALL. COLUMNS : 4 @ GL: G/3 - 4.1 (CC2A); G/1 (CC1), E/6 (CC5.3). OK TO PLACE CONCRETE.
07/10/2018 EXCAVATION/LAYOUT REBAR & ZON Partial Approval COLUMNS AT GL: E/5, (CC4); D/6.1 (CC5): WALL FOOTINGS AT GL: 3.2/A - B.5; A/3.2 - 3.9. OK TO PLACE CONCRETE.
07/05/2018 EXCAVATION/LAYOUT REBAR & ZON Partial Approval FOOTING (F1) AT GL: 7/A - H.9, OK TO PLACE CONCRETE IN PROGRESS AREAS.
07/03/2018 EXCAVATION/LAYOUT REBAR & ZON Partial Approval FOOTING (F4) AT GL: A/3.9 - 7. OK TO PLACE CONCRETE.
07/02/2018 EXCAVATION/LAYOUT REBAR & ZON Partial Approval CAISSON FOOTING CAGES (19) AT DSF: 1, 1.4, 1.5, 1.6, 1.7, 1.8, 6.10, 6.11, 6.12, 6.8, 6.9, 5.1, 9, 9.1.
CM-1 WALL AT GL: E.2-E.5/1.5-2; 1.5/E.9- F. OK TO PLACE CONCRETE IN PROGRESS AREAS.
06/28/2018 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :* LOWEST LEVEL OF ELEVATOR PIT WALLS OK TO POUR
06/27/2018 EXCAVATION/LAYOUT REBAR & ZON Partial Approval CAISSON FOOTING CAGES (12) TO BE SET IN FOOTINGS AT GL: A-F/6-7: B/4-5. #DSF: 1, 1.2, 1.1, 2, 4.2, 5.2, 5.3, 6, 6.5, 6.6. OK TO PLACE REBAR CAGES.
06/26/2018 EXCAVATION/LAYOUT REBAR & ZON Partial Approval STAIRWELL #1 WALL AT GL: 3.2/A-C. OK TO PLACE CONCRETE.
06/25/2018 EXCAVATION/LAYOUT REBAR & ZON Partial Approval NORTH EAST STAIR WELL FOOTING (F4) AT GL: E.5-F.2/1.3-1.5. COLUMNS (3) AT GL: D/3.2; 3.2/D; E/4. SHEAR WALL #7; STAIRWELL #2 WALLS. OK TO PLACE CONCRETE IN PROGRESS AREAS.
06/19/2018 EXCAVATION/LAYOUT REBAR & ZON Partial Approval BASE OF NORTHEAST ELEVATOR OK TO POUR
06/08/2018 EXCAVATION/LAYOUT REBAR & ZON Partial Approval EAST STAIRWELL GRADE BEAMS OK TO POUR. NORTHEAST ELEVATOR SHAFT OK TO POUR GRADE BEAMS.
06/07/2018 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection
06/06/2018 EXCAVATION/LAYOUT REBAR & ZON Partial Approval GRADE BEAMS AT NORTHWEST STAIRWAY OK TO POUR
06/01/2018 EXCAVATION/LAYOUT REBAR & ZON Partial Approval CAISONS IN ELEVATOR PIT TOP OFF
GRADE BEAM AND FOOTING NORTH SIDE OF PIT
OK TO PLACE CONCRETE
05/25/2018 EXCAVATION/LAYOUT REBAR & ZON Partial Approval CAISONS AT GRIDLINES D & E / 2, 3.2, 4, 5 AND B & C / 2.5, 3.2, 3.5, AND C/5, C/4 ALL OK TO PLACE CONCRETE
05/23/2018 EXCAVATION/LAYOUT REBAR & ZON Partial Approval SIX CAISONS (GL E.7/2,2.2,3.1 & GL F/2,2.2,3.1) OK TO POUR