Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit: T17FC00923

Parcel: 14043013B

Inspection Status: Approved

Inspection History: FIRE SPKLR - UG, PIPING, HYDRO

Permit Number - T17FC00923

Inspection Description - FIRE SPKLR - UG, PIPING, HYDRO

Inspection Status - Approved

Date Description Inspector Results Comments
03/28/2018 FIRE SPKLR - UG, PIPING, HYDRO Approved 3D Contractors to assume all liability for the underground line. Line was partialled and covered without hydro numerouse times. 3D and Brassfield Gorrie paperwork signed by them also stated that they were assuming liability
03/27/2018 FIRE SPKLR - UG, PIPING, HYDRO Approved
03/09/2018 FIRE SPKLR - UG, PIPING, HYDRO Partial Approval wanted a PA on a section of UG. Told Juan we would accept Raytheons approval or to call it in for Monday since Inspector JPD knows the project and is allowing visual inspections. Juan will be taking pics.
01/10/2018 FIRE SPKLR - UG, PIPING, HYDRO Partial Approval 1/3 of the building on the south side. 2 PIV, no pressure , no hydro, no flush. All will still need to be performed. This is a phase project.
12/28/2017 FIRE SPKLR - UG, PIPING, HYDRO Partial Approval Ok to cover underground from pump house to building. Still need to hydro test. Supply to pump house still need full inspection. Extra inspection fee will apply as they will need several partials. 1 of 2.
12/26/2017 FIRE SPKLR - UG, PIPING, HYDRO Denied No access, gate closed not entry to Raytheon.