Inspection Status: Passed
Inspection History: COT - HCPL - Plumbing Final
| Date |
Description |
Inspector |
Results |
Comments |
| 04/16/2019 |
COT - HCPL - Plumbing Final |
RCAMACHO |
Partial Approval |
Entered by AVAUGHN1 - Pending fire and engineering finals
|
| 04/16/2019 |
COT - HCPL - Plumbing Final |
RCAMACHO |
Approved |
Entered by CMURPHY1 - Pending fire and engineering finals
Pending chlorination report from Bob Sherry |
| 04/08/2019 |
COT - HCPL - Plumbing Final |
RCAMACHO |
Partial Approval |
Entered by CBELL1 - ADA water closet not to exceed 18 inches from wall Fitness center
Install ADA mirrors fitness center restrooms
Pending air balance report and chlorination report to Bob Sherry |
| 03/01/2019 |
COT - HCPL - Plumbing Final |
RSHERRY |
Partial Approval |
Entered by RSHERRY1 - REVIEW OF WATER DISINFECTION REPORT FOR THE 1ST FLOOR COMPLETED |
| 02/28/2019 |
COT - HCPL - Plumbing Final |
RCAMACHO |
Partial Approval |
Entered by CBELL1 - Except fitness center and sterilization report to Bob Sherry |
| 02/27/2019 |
COT - HCPL - Plumbing Final |
RCAMACHO |
Partial Approval |
Entered by CBELL1 - Inspection to roof area only except patio at west balcony area
Clear up all open inspections prior to next final inspection |
| 01/17/2019 |
COT - HCPL - Plumbing Final |
RCAMACHO |
Partial Approval |
Entered by CBELL1 - Level two only fire seal caulk all penetrations 2-hour firewall storage room
Seal penetration at fire shaft at duck work in core |
| 12/18/2018 |
COT - HCPL - Plumbing Final |
RCAMACHO |
Partial Approval |
Entered by CBELL1 - level 3 ada water closet men’s restroom may not exceed 18 inches from wall
level 3 women’s restroom ada counter may not exceed 34 inches
Pending fire & engineering, pending air balance report and chlorination report to Bob Sherry OK to apply for temporary CEO level 3 only |
| 12/14/2018 |
COT - HCPL - Plumbing Final |
RSHERRY |
Partial Approval |
Entered by RSHERRY1 - REVIEW OF WATER DISINFECTION REPORTS FOR 2ND &3RD FLOOR COMPLETED |