Permit: T17CM08953

Parcel: 11620134B


Addresses:

875 W CUSHING ST

Inspection Status: Passed

Inspection History: COT - HCEL - Electrical Underground 

Date Description Inspector Results Comments
03/15/2019 COT - HCEL - Electrical Underground  Passed {Activity date: 03/15/2019; Status: Approved; Inspector: RCAMACHO; Comment: Entered by CBELL1 - To include monument sign footings} ; {Activity date: 03/06/2019; Status: Partial Approval; Inspector: RCAMACHO; Comment: Entered by CBELL1 - NE corner at walkway Ballard lighting only} ; {Activity date: 02/28/2019; Status: Partial Approval; Inspector: RCAMACHO; Comment: Entered by CBELL1 - Except NW corner by road
Except NE corner by stair 3 walkway} ; {Activity date: 02/15/2019; Status: Partial Approval; Inspector: RCAMACHO; Comment: Entered by CBELL1 - Ballard light in zone 3 west} ; {Activity date: 02/14/2019; Status: Partial Approval; Inspector: RCAMACHO; Comment: Entered by CBELL1 - Completion of light pole bases} ; {Activity date: 02/12/2019; Status: Partial Approval; Inspector: BSTEVENS; Comment: Entered by CBELL1 - Zone two NE. walkway underground electrical OK to cover} ; {Activity date: 02/08/2019; Status: Partial Approval; Inspector: BSTEVENS; Comment: Entered by CBELL1 - Entry turn styles and parking lot zone six underground OK to cover.} ; {Activity date: 02/05/2019; Status: Partial Approval; Inspector: RCAMACHO; Comment: Entered by CBELL1 - 11 Pole bases zone number six only} ; {Activity date: 01/28/2019; Status: Partial Approval; Inspector: TVALENCIA; Comment: Entered by CBELL1 - 1- Underground lightning #1/0 copper stranded ground conductor provided from grid line#1 to grid line #12 only, okay to cover.
2- Underground electric conduits from North side of bldg. grid line #7 to site lighting is okay to cover.
3- MC cable and metal boxes and light fixtures are okay to cover at East patio ceiling only.} ; {Activity date: 01/25/2019; Status: Partial Approval; Inspector: DQUINN; Comment: Entered by CBELL1 - Site lighting conduit west of bridge and west of garage OK to cover. Conduit west of visitor parking OK to cover.} ; {Activity date: 01/18/2019; Status: Not ready for Inspection; Inspector: RCAMACHO; Comment: Entered by CBELL1 - no work} ; {Activity date: 01/17/2019; Status: Partial Approval; Inspector: RCAMACHO; Comment: Entered by CBELL1 - Zone six garage gate only} ; {Activity date: 01/16/2019; Status: Not ready for Inspection; Inspector: RCAMACHO; Comment: Entered by CBELL1 - no work} ; {Activity date: 01/15/2019; Status: Partial Approval; Inspector: RCAMACHO; Comment: Entered by CBELL1 - Zone six except a gate and pole bases} ; {Activity date: 01/14/2019; Status: Partial Approval; Inspector: RCAMACHO; Comment: Entered by CBELL1 - 14 x 1" zone 2 at lobby only} ; {Activity date: 01/11/2019; Status: Partial Approval; Inspector: RCAMACHO; Comment: Entered by CBELL1 - Zone 2 Ballard lighting GL 1-3} ; {Activity date: 12/26/2018; Status: Partial Approval; Inspector: RCAMACHO; Comment: Entered by CBELL1 - Completion of zone 2 ballard lighting south area only} ; {Activity date: 12/19/2018; Status: Partial Approval; Inspector: RCAMACHO; Comment: Entered by CBELL1 - Valor lighting zone to Gridline five and Gridline three only} ; {Activity date: 12/11/2018; Status: Partial Approval; Inspector: RCAMACHO; Comment: Entered by CBELL1 - Ballard lighting by bike rack zone 2} ; {Activity date: 12/07/2018; Status: Partial Approval; Inspector: RCAMACHO; Comment: Entered by CBELL1 - Underground at elevator entry turnstile only
Ballard lighting zone one to lobby area} ; {Activity date: 12/03/2018; Status: Partial Approval; Inspector: RCAMACHO; Comment: Entered by CBELL1 - Level 1 garage grid line 1-6 from E- H only} ; {Activity date: 11/28/2018; Status: Partial Approval; Inspector: RCAMACHO; Comment: Entered by CBELL1 - 1 × 1" at North canopy parking only 1 × 1 1/2 inch to cameras to East canopies} ; {Activity date: 11/26/2018; Status: Partial Approval; Inspector: RCAMACHO; Comment: Entered by CBELL1 - TCO pre con meeting in office} ; {Activity date: 11/20/2018; Status: Partial Approval; Inspector: RCAMACHO; Comment: Entered by CBELL1 - From garage to 30 foot North Buy pull box only
Grounding Loop West End only} ; {Activity date: 11/16/2018; Status: Not ready for Inspection; Inspector: RCAMACHO; Comment: Entered by CBELL1 - Work not complete West End} ; {Activity date: 11/13/2018; Status: Partial Approval; Inspector: RCAMACHO; Comment: Entered by CBELL1 - Grounding loop north GL 4-10 with 2 ground rods} ; {Activity date: 11/08/2018; Status: Partial Approval; Inspector: RCAMACHO; Comment: Entered by CBELL1 - 1 x 3/4 " from ballards to accross road} ; {Activity date: 11/06/2018; Status: Partial Approval; Inspector: RCAMACHO; Comment: Entered by CBELL1 - 1 x 3/4" at bollard lighting, security camera and to pole base in zone 1 only} ; {Activity date: 10/25/2018; Status: Partial Approval; Inspector: RCAMACHO; Comment: Entered by CBELL1 - Top out Fitness Center
In fill at mechanical yard
retaining wall patio area East} ; {Activity date: 10/19/2018; Status: Partial Approval; Inspector: ESTEVENS; Comment: Entered by CBELL1 - Two four-inch PVC, data lines northeast corner} ; {Activity date: 10/12/2018; Status: Partial Approval; Inspector: RCAMACHO; Comment: Entered by CBELL1 - 2 x 4" low voltage at Avenida Convento property line} ; {Activity date: 10/09/2018; Status: Not ready for Inspection; Inspector: RCAMACHO; Comment: Entered by CBELL1 - } ; {Activity date: 10/08/2018; Status: Partial Approval; Inspector: RCAMACHO; Comment: Entered by VFLORES1 - 5 x 1" GL 5 from J-M Garage} ; {Activity date: 10/04/2018; Status: Partial Approval; Inspector: RCAMACHO; Comment: Entered by CMURPHY1 - 3 x 1" GL 5 from A-I

3 X 1" from column D/6 GL 5 to GL I

1 X 1 1/2" from column D/6 GL 5 to GL H

2 X 1" from panel to GL 6 to C-D

2 X 1" from panel to GL 6 to B} ; {Activity date: 09/21/2018; Status: Partial Approval; Inspector: RCAMACHO; Comment: Entered by CMURPHY1 - 5 x 3 1/2" to 10' short of switchgear

2 x 2 1/2" chiller lines

2 x 3/4" & 2 x 1" same locations mechanical yard} ; {Activity date: 09/20/2018; Status: Partial Approval; Inspector: RCAMACHO; Comment: Entered by CMURPHY1 - 17 x 4" secondaries and risers at transformer} ; {Activity date: 09/13/2018; Status: Partial Approval; Inspector: RCAMACHO; Comment: Entered by CMURPHY1 - F-1 & F-2 footers Garage GL MG -FG from 1G- 6G 28 Footings total
See highlighted S1.1.0 plan
Completion of east exterior wall only
SES uaerd 1st lift only
2 x 2" & 1 x 1" from loading and receiving to trench C and to mech yard
Trench C to mech uard 5 x 3 1/2 " * 2 x 1"

} ; {Activity date: 09/10/2018; Status: Partial Approval; Inspector: RCAMACHO; Comment: Entered by CMURPHY1 - 14 x4 in & 3 x 3 in from SES yard to Transformer

4 x 4in, 3 x 3", 2 x 1 1/2 inch, 5 x1 in from S&R to West 120-foot only} ; {Activity date: 08/20/2018; Status: Partial Approval; Inspector: ESTEVEN1; Comment: Entered by ESTEVEN1 - THREE 3" PVC FOR SOLAR PV, 20' OUT FRO BUILDING.} ; {Activity date: 08/03/2018; Status: Partial Approval; Inspector: RCAMACHO; Comment: Entered by RCAMACH1 - 3 X 3" GL 3-4 FROM A-C LEVEL 3} ; {Activity date: 08/01/2018; Status: Partial Approval; Inspector: RCAMACHO; Comment: Entered by RCAMACH1 - AFTER HOURS INSPECTION $165.00 RECEIVED CHECK # 2709
MAKERS SPACE GL 10-13 1ST LEVEL} ; {Activity date: 08/01/2018; Status: Partial Approval; Inspector: RCAMACH1; Comment: Entered by RCAMACH1 - IVRS - Inspection :*
SECONDARY 1 X 3" FROM TRANSFORMER TO TEMP POWER PANEL ONLY} ; {Activity date: 07/30/2018; Status: Partial Approval; Inspector: RCAMACH1; Comment: Entered by RCAMACH1 - IVRS - Inspection :*
1ST LEVEL GL 1-3 FROM A-C.5 ONLY} ; {Activity date: 07/25/2018; Status: Partial Approval; Inspector: RCAMACHO; Comment: Entered by RCAMACH1 - ROOMS 1029 & 1010} ; {Activity date: 07/19/2018; Status: Partial Approval; Inspector: RCAMACH1; Comment: Entered by RCAMACH1 - GL A-C FROM 8-14 ONLY} ; {Activity date: 07/17/2018; Status: Partial Approval;