Inspection History Details
Inspection Status: Passed
Inspection History: COT - HCBU - Excavation/Rebar/Zoning
Permit Number - T17CM08953
Inspection Description - COT - HCBU - Excavation/Rebar/Zoning
Inspection Status - Passed
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 04/08/2019 | COT - HCBU - Excavation/Rebar/Zoning | RCAMACHOI | Approved | Entered by CBELL1 - |
| 02/14/2019 | COT - HCBU - Excavation/Rebar/Zoning | RCAMACHO | Partial Approval | Entered by CBELL1 - Completion of light pole bases |
| 02/05/2019 | COT - HCBU - Excavation/Rebar/Zoning | RCAMACHO | Partial Approval | Entered by CBELL1 - 11 Pole bases zone number six only |
| 01/15/2019 | COT - HCBU - Excavation/Rebar/Zoning | RCAMACHO | Not ready for Inspection | Entered by CBELL1 - work incomplete |
| 01/11/2019 | COT - HCBU - Excavation/Rebar/Zoning | RCAMACHO | Partial Approval | Entered by CBELL1 - Stairs to Parking lot bottom mat only See RFI 232 drill and Epoxy Gridline 3 pending special inspection |
| 12/27/2018 | COT - HCBU - Excavation/Rebar/Zoning | RCAMACHO | Partial Approval | Entered by CBELL1 - GL 3 wf2 footing per detail 110 |
| 12/14/2018 | COT - HCBU - Excavation/Rebar/Zoning | RCAMACHO | Partial Approval | Entered by CBELL1 - Stairs north garage per detail 417/s6.2 |
| 11/21/2018 | COT - HCBU - Excavation/Rebar/Zoning | RCAMACHO | Partial Approval | Entered by CBELL1 - See rfi 153 per detail 24 Water meter enclosure only |
| 11/09/2018 | COT - HCBU - Excavation/Rebar/Zoning | RCAMACHO | Partial Approval | Entered by CBELL1 - Mw2 wall per detail 110 GL 10 from C-E.5 pending special insp report See highlighted plan |
| 10/26/2018 | COT - HCBU - Excavation/Rebar/Zoning | RCAMACHO | Partial Approval | Entered by CBELL1 - F3 footers bike yard GL 7 frin D.6-E.6 |
| 10/08/2018 | COT - HCBU - Excavation/Rebar/Zoning | RCAMACHO | Partial Approval | Entered by VFLORES1 - 10' wall footing at long trrm bike parking per detail24 and interior f-3 footers See highlighted s2.1.a plan Patio wall GL 24 from a-c per detail 25 See highlighted plan s2.1.b |
| 10/05/2018 | COT - HCBU - Excavation/Rebar/Zoning | RCAMACHO | Partial Approval | Entered by CMURPHY1 - Verification of grade garage columns |
| 10/04/2018 | COT - HCBU - Excavation/Rebar/Zoning | RCAMACHO | Partial Approval | Entered by CMURPHY1 - Verification of grade garage columns |
| 09/28/2018 | COT - HCBU - Excavation/Rebar/Zoning | RCAMACHO | Partial Approval | Entered by CMURPHY1 - patio curb level 3 see rfi 280 |
| 09/24/2018 | COT - HCBU - Excavation/Rebar/Zoning | MRAMBER | Not ready for Inspection | Entered by CMURPHY1 - |
| 09/20/2018 | COT - HCBU - Excavation/Rebar/Zoning | RCAMACHO | Denied | Entered by CMURPHY1 - Footer column A/4 provide proper clearance steel from soil |
| 09/18/2018 | COT - HCBU - Excavation/Rebar/Zoning | RCAMACHO | Partial Approval | Entered by CMURPHY1 - F-1 & F-3 garage footers colum. A/5 with ground A/3 & A2 see highlighted s1.1.0 plan |
| 09/17/2018 | COT - HCBU - Excavation/Rebar/Zoning | RCAMACHO | Partial Approval | Entered by CMURPHY1 - Garage F-1, F-2 & F-3 footers B/1, C/1, D/1,E/1, C/3, D/3, E/3, C/4, D/4, E/4, B/6, C/6, D/6& E/6 see highlighted plan s1.1.0 |
| 09/17/2018 | COT - HCBU - Excavation/Rebar/Zoning | RCAMACHO | Partial Approval | Entered by CMURPHY1 - TES CALL CTR ROOM 3097 Elevator pit per detail 117 see rfi 281 10" oc each way top and bottom Rooms 3091, 3093, 3094, 3095, 3096 & 3097 GL A-C from 11-14 LEVEL 3 |
| 09/13/2018 | COT - HCBU - Excavation/Rebar/Zoning | RCAMACHO | Partial Approval | Entered by CMURPHY1 - F-1 & F-2 footers Garage GL MG -FG from 1G- 6G 28 Footings total See highlighted S1.1.0 plan Completion of east exterior wall only SES uaerd 1st lift only 2 x 2" & 1 x 1" from loading and receiving to trench C and to mech yard Trench C to mech uard 5 x 3 1/2 " * 2 x 1" |
| 09/12/2018 | COT - HCBU - Excavation/Rebar/Zoning | RCAMACHO | Not ready for Inspection | Entered by CMURPHY1 - Exterior west walls only ok to cover |
| 08/29/2018 | COT - HCBU - Excavation/Rebar/Zoning | RCAMACHO | Partial Approval | Entered by VFLORES1 - SES yard only |
| 07/02/2018 | COT - HCBU - Excavation/Rebar/Zoning | RCAMACHO | Partial Approval | Entered by RCAMACH1 - STAIRWELL 2 ONLY |
| 07/02/2018 | COT - HCBU - Excavation/Rebar/Zoning | RCAMACH1 | Partial Approval | Entered by RCAMACH1 - IVRS - Inspection :* |
| 05/17/2018 | COT - HCBU - Excavation/Rebar/Zoning | RCAMACHO | Partial Approval | Entered by RCAMACH1 - GL 3 FROM B TO C PER DETAIL 110 PENDING SI REPORT FOR EPOXY |
| 05/16/2018 | COT - HCBU - Excavation/Rebar/Zoning | RCAMACHO | Denied | Entered by RCAMACH1 - FOOTING TO BE CONTINOUS GL C EPOXY TO COLUMN FOOTINGS |
| 05/15/2018 | COT - HCBU - Excavation/Rebar/Zoning | RCAMACHO | Partial Approval | Entered by RCAMACH1 - MECH YARD FOOTER PER DETAIL A/S2.1.C SEE HIGHLIGHTED AREA WITH STEP DOWN FOOTING |
| 05/11/2018 | COT - HCBU - Excavation/Rebar/Zoning | rbaldwin | Partial Approval | Entered by RBALDWI2 - MECHANICAL YARD FOOTINGS PER DETAIL 1S2.1C OK TO POUR |
| 05/10/2018 | COT - HCBU - Excavation/Rebar/Zoning | RBALDWIN | Partial Approval | Entered by RBALDWI2 - SOUTH END OF FOOTINGS TO FIRST STEPOK PER DETAIL A 52C |
| 05/09/2018 | COT - HCBU - Excavation/Rebar/Zoning | RBALDWIN | Cancelled | Entered by RBALDWI2 - |
| 05/08/2018 | COT - HCBU - Excavation/Rebar/Zoning | RCAMACHO | Not ready for Inspection | Entered by RCAMACH1 - NO VERTS IN PLACE MECH YARD |
| 05/08/2018 | COT - HCBU - Excavation/Rebar/Zoning | RCAMACHO | Not ready for Inspection | Entered by RCAMACH1 - |
| 04/24/2018 | COT - HCBU - Excavation/Rebar/Zoning | RCAMACHO | Partial Approval | Entered by RCAMACH1 - NE STAIRWELL GARAGE PRE DETAIL 414 NORTH RETAINING WALL FOOTER GL A FROM 5.5 TO 7 PER DETAIL 25 WEST BRIDGE RETAINING WALL FOOTER GL 1 FROM E-F PER DETAIL 25 ONLY |
| 04/23/2018 | COT - HCBU - Excavation/Rebar/Zoning | RCAMACHO | Denied | Entered by RCAMACH1 - PROVIDE PROPER CLEARANCE 3" REBAR FROM SOIL THROUGHOUT REMOVE ALL DEBRIS PRIOR |
| 02/14/2018 | COT - HCBU - Excavation/Rebar/Zoning | RCAMACHO | Partial Approval | Entered by RCAMACH1 - GRADE BEAMS 1 & 3 WITH DEATIL 112 FOOTERS GRID LINE 1 FROM A-F GRADE BEAMS 1 & 3 GRID LINE D FROM 1-3 GRADE BEAM 2 GRID LINE 7.2 FROM D-E EXCEPT EPOXY #5 VERTS 20' AREA GRADE BEAM 2 GRID LINE F FROM 7.2 TO 9.5 GRADE BEAM 2 GRID LINE 9.5 FROM D-F EXCEPT EPOXY #5 VERTS 20' AREA SEE HIGHLIGHTED AREA |