Inspection History Details
Inspection Status: Approved
Inspection History: MECHANICAL - ABOVE CEILING
Permit Number - T17CM08216
Inspection Description - MECHANICAL - ABOVE CEILING
Inspection Status - Approved
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 07/21/2021 | MECHANICAL - ABOVE CEILING | Approved | Approved | |
| 10/07/2020 | MECHANICAL - ABOVE CEILING | Partial Approval | Partial. Room Units 230; 232; 323; 324; 325; 326. | |
| 09/11/2020 | MECHANICAL - ABOVE CEILING | Partial Approval | Partial. Level #6; Room Units #612-622. Ok to insulate and cover walls. | |
| 09/08/2020 | MECHANICAL - ABOVE CEILING | Partial Approval | Partial. Level #5; Room Units 517; 519; 520; 521. | |
| 09/03/2020 | MECHANICAL - ABOVE CEILING | Partial Approval | Partial. Waste and vent lines in Room Units #512; 515 on Level,#5. | |
| 09/02/2020 | MECHANICAL - ABOVE CEILING | Not ready for Inspection | Not ready. Contractor cancelled will reschedule for 3 September | |
| 08/26/2020 | MECHANICAL - ABOVE CEILING | Partial Approval | Partial. Level #4; Room Units 412; 415; 417; 421; 422. | |
| 08/21/2020 | MECHANICAL - ABOVE CEILING | Not ready for Inspection | Not ready. Contractor cancelled. | |
| 08/19/2020 | MECHANICAL - ABOVE CEILING | Partial Approval | Partial. Level #3; Room Units #312-322 | |
| 08/10/2020 | MECHANICAL - ABOVE CEILING | Not ready for Inspection | Not ready. Contractor cancelled. | |
| 07/31/2020 | MECHANICAL - ABOVE CEILING | Partial Approval | Partial. Building C; Level #2; Room Units #217; 219; 220; 221; 222. | |
| 07/29/2020 | MECHANICAL - ABOVE CEILING | Partial Approval | Partial. Building C; Level #6 Room Units # 604; 606; 609; 610; 645. Building D, Level #2; Room Units #212; 215. | |
| 07/27/2020 | MECHANICAL - ABOVE CEILING | Not ready for Inspection | Not ready. Contractor cancelled. Inspections will be rescheduled for 29 July. | |
| 06/23/2020 | MECHANICAL - ABOVE CEILING | Partial Approval | Partial. Level #4; duct system in place in 402; 404; 406; 408; 409; 410; 411; 445. | |
| 06/12/2020 | MECHANICAL - ABOVE CEILING | Partial Approval | Partial. Level #3; Duct works in rooms: 300; 302; 306; 308; 309; 310; 311; 345 | |
| 06/08/2020 | MECHANICAL - ABOVE CEILING | Not ready for Inspection | Not ready, contractor cancelled. | |
| 06/04/2020 | MECHANICAL - ABOVE CEILING | Not ready for Inspection | Not ready. Contractor cancelled. | |
| 04/08/2020 | MECHANICAL - ABOVE CEILING | Partial Approval | VRI ROOM 650 | |
| 03/11/2020 | MECHANICAL - ABOVE CEILING | Partial Approval | Buildings A&B, corridors A&B, floors 2&3. |