Inspection Status: Approved
Inspection History: PLUMBING - ABOVE CEILING
Permit Number - T17CM08216
Inspection Description - PLUMBING - ABOVE CEILING
Inspection Status - Approved
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 12/29/2021 | PLUMBING - ABOVE CEILING | Approved | ||
| 12/01/2020 | PLUMBING - ABOVE CEILING | Partial Approval | Partial. Levels 2-6; Waste and vent lines; domestic water (Pex lines) under test. | |
| 11/30/2020 | PLUMBING - ABOVE CEILING | Cancelled | IVRS - AP canceled | |
| 11/04/2020 | PLUMBING - ABOVE CEILING | Not ready for Inspection | Not ready. Contractor cancelled, will reschedule for 5 November. | |
| 11/02/2020 | PLUMBING - ABOVE CEILING | Cancelled | IVRS - AP canceled | |
| 10/07/2020 | PLUMBING - ABOVE CEILING | Partial Approval | Partial. Room Units 230; 232; 323; 324; 325; 326. | |
| 09/11/2020 | PLUMBING - ABOVE CEILING | Partial Approval | Partial. Level #6; Room Units #612 - 622 | |
| 09/08/2020 | PLUMBING - ABOVE CEILING | Approved | Partial. Level #5; Room Units 517; 519; 520; 521. | |
| 06/30/2020 | PLUMBING - ABOVE CEILING | Approved | Partial. Levels #2&3; Section corridors C & D.. | |
| 06/17/2020 | PLUMBING - ABOVE CEILING | Not ready for Inspection | Not ready. Contractor cancelled. | |
| 06/04/2020 | PLUMBING - ABOVE CEILING | Partial Approval | Partial. Level #2; Sections C & D; water main line (2”-4”) | |
| 05/20/2020 | PLUMBING - ABOVE CEILING | Not ready for Inspection | Not ready. Contractor cancelled. | |
| 05/19/2020 | PLUMBING - ABOVE CEILING | Cancelled | ||
| 05/18/2020 | PLUMBING - ABOVE CEILING | Not ready for Inspection | Not ready. Contractor cancelled, main line cut for repairs. | |
| 04/08/2020 | PLUMBING - ABOVE CEILING | Partial Approval | VRI ROOM 650 | |
| 03/11/2020 | PLUMBING - ABOVE CEILING | Partial Approval | Buildings A&B, corridors A&B, floors 2&3. |