Inspection Status: Approved
Inspection History: BUILDING - FINAL
| Date |
Description |
Inspector |
Results |
Comments |
| 12/29/2021 |
BUILDING - FINAL |
|
Approved |
|
| 12/27/2021 |
BUILDING - FINAL |
|
Partial Approval |
REVIEW OF WATER DISINFECTION REPORT FOR PHASE 2 COMPLETED |
| 12/27/2021 |
BUILDING - FINAL |
|
Partial Approval |
Partial. Need to complete Applied permits. (T19CM00524) (T19CM02786). |
| 12/27/2021 |
BUILDING - FINAL |
|
Partial Approval |
REVIEW OF REVISED AIR BALANCE REPORT COMPLETED |
| 12/23/2021 |
BUILDING - FINAL |
|
Not ready for Inspection |
Not ready. Need units on Level cleared. |
| 08/30/2021 |
BUILDING - FINAL |
|
Partial Approval |
REVIEW OF WATER DISINFECTION REPORT COMPLETED |
| 08/30/2021 |
BUILDING - FINAL |
|
Correction Required |
AIR BALANCE SHOWS L1-7A IS ONLY MOVING 45% OF THE REQUIRED 200 CFM EXHAUST FLOW RATE |
| 08/27/2021 |
BUILDING - FINAL |
|
Partial Approval |
Partial. TCO walk through for North half of project. |
| 06/28/2021 |
BUILDING - FINAL |
|
Not ready for Inspection |
NOT READY INSPECTIONS ARE NOT COMPLETE |
| 06/24/2021 |
BUILDING - FINAL |
|
Not ready for Inspection |
Not ready. Contractor cancelled will reschedule for 28 June. |
| 03/18/2021 |
BUILDING - FINAL |
|
Not ready for Inspection |
NOT READY CANCELLED BY CONTRACTOR |
| 03/16/2021 |
BUILDING - FINAL |
|
Not ready for Inspection |
Not ready. Contractor cancelled. |
| 04/16/2020 |
BUILDING - FINAL |
|
Not ready for Inspection |
ENTRY MODIFIED BY JIM BURGE AND RICK SALDATE, PROJECT IS LARGE AND STILL NEEDS ADDITIONAL INSPECTIONS BY JBURGE. |