Inspection History Details
Inspection Status: Approved
Inspection History: BUILDING - FINAL
Permit Number - T17CM08216
Inspection Description - BUILDING - FINAL
Inspection Status - Approved
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 12/29/2021 | BUILDING - FINAL | Approved | ||
| 12/27/2021 | BUILDING - FINAL | Partial Approval | REVIEW OF WATER DISINFECTION REPORT FOR PHASE 2 COMPLETED | |
| 12/27/2021 | BUILDING - FINAL | Partial Approval | Partial. Need to complete Applied permits. (T19CM00524) (T19CM02786). | |
| 12/27/2021 | BUILDING - FINAL | Partial Approval | REVIEW OF REVISED AIR BALANCE REPORT COMPLETED | |
| 12/23/2021 | BUILDING - FINAL | Not ready for Inspection | Not ready. Need units on Level cleared. | |
| 08/30/2021 | BUILDING - FINAL | Partial Approval | REVIEW OF WATER DISINFECTION REPORT COMPLETED | |
| 08/30/2021 | BUILDING - FINAL | Correction Required | AIR BALANCE SHOWS L1-7A IS ONLY MOVING 45% OF THE REQUIRED 200 CFM EXHAUST FLOW RATE | |
| 08/27/2021 | BUILDING - FINAL | Partial Approval | Partial. TCO walk through for North half of project. | |
| 06/28/2021 | BUILDING - FINAL | Not ready for Inspection | NOT READY INSPECTIONS ARE NOT COMPLETE | |
| 06/24/2021 | BUILDING - FINAL | Not ready for Inspection | Not ready. Contractor cancelled will reschedule for 28 June. | |
| 03/18/2021 | BUILDING - FINAL | Not ready for Inspection | NOT READY CANCELLED BY CONTRACTOR | |
| 03/16/2021 | BUILDING - FINAL | Not ready for Inspection | Not ready. Contractor cancelled. | |
| 04/16/2020 | BUILDING - FINAL | Not ready for Inspection | ENTRY MODIFIED BY JIM BURGE AND RICK SALDATE, PROJECT IS LARGE AND STILL NEEDS ADDITIONAL INSPECTIONS BY JBURGE. |