Inspection History Details
Inspection Status: Approved
Inspection History: BUILDING - PROGRESS
Permit Number - T17CM08216
Inspection Description - BUILDING - PROGRESS
Inspection Status - Approved
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 12/27/2021 | BUILDING - PROGRESS | Approved | Approved. Level #2; Units #221-228; 230-244; 246; 248. Level #1; Units; 122, 124, 126; 128; 130; 132. | |
| 12/23/2021 | BUILDING - PROGRESS | Partial Approval | Partial. Level #3 Units: #321-328; 330-344; 346, 348. Appliances are in place. | |
| 12/21/2021 | BUILDING - PROGRESS | Partial Approval | Partial. Level #4; Units: 421-428; 430-444: 446,448. Units are complete; appliances are in place. | |
| 12/20/2021 | BUILDING - PROGRESS | Not ready for Inspection | Not ready. Level #4; ADA Units are not ready. Washer/dryer to be replaced. | |
| 12/16/2021 | BUILDING - PROGRESS | Partial Approval | Partial. Level #5; Units 3521-528; 530-544; 546,548. Level #5 Room units are complete. | |
| 12/15/2021 | BUILDING - PROGRESS | Not ready for Inspection | Not ready. Contractor cancelled. Will reschedule for 16 December. | |
| 12/14/2021 | BUILDING - PROGRESS | Not ready for Inspection | Not ready. Contractor cancelled. All appliances are not in on Level #5. Will recall when in place. | |
| 12/13/2021 | BUILDING - PROGRESS | Partial Approval | Partial. Level #6; Room Units: 621-629: 630-644; 646; 648. All appliances are in place; Room Units are complete. | |
| 11/04/2021 | BUILDING - PROGRESS | Partial Approval | Partial. Electric meters for panels and room units: Section H, Level #1: 122, 124, 126, 128, 130, 132 CLEARANCE, Code: ECO |
|
| 10/14/2021 | BUILDING - PROGRESS | Partial Approval | Partial. Level #1; Section H-1, corridor and ceiling: all penetrations Fire stopped. | |
| 10/06/2021 | BUILDING - PROGRESS | Partial Approval | Partial. Room finals in Sections E and F: Level #2 Rooms 212-220; Level #3 Rooms 312-320; Level #4 Rooms 412-420. | |
| 10/04/2021 | BUILDING - PROGRESS | Partial Approval | Partial. Room finals in Sections C-D Level #5: 502-511; Level #6: 602-611; Sections E-F, Level 5, 502-511; Level #6, 612-620; | |
| 09/22/2021 | BUILDING - PROGRESS | Partial Approval | Partial. Information for Temporary Certificate of Occupancy. | |
| 09/17/2021 | BUILDING - PROGRESS | Partial Approval | Partial. ECO Meters and room panels to be energized: Section H, Level #1: 122, 124,126, 128, 130, 132. Section G, Level #2: 232, 240, 248. Section G, Level #3: 341, 342, 343, 344, 346, 348. Section G, Level #4: 441, 442, 443, 444, 446, 448. Section G, Level #5: 541, 542, 543, 544, 546, 548. Section D, Level #6: 602, 645. Section G, Level #6: 632, 639, 642, 648. Section I, Level #6: 631, 633, 634, 635, 636, 637, 638, 640. | |
| 09/15/2021 | BUILDING - PROGRESS | Partial Approval | Partial. Information concerning access panels in level #2 of parking garage | |
| 09/10/2021 | BUILDING - PROGRESS | Partial Approval | . Partial. Unit panels and meters: Section H, Level #1: 122, 124, 126, 128, 130, 132; Section G, Level #2: 232, 240, 248; Section G; Level #3: 341, 342, 343, 344, 346, 348; Section G, Level #4: 441, 442, 443, 444, 446, 448; Section G; Level #5: 541, 542, 543, 544, 546, 548; Section D, Level #6; 602, 645; Section G, Level #6; 632, 639, 642, 648; Section I, Level #6; 631, 633, 635, 637, 634, 636, 638, 64 | |
| 08/31/2021 | BUILDING - PROGRESS | Partial Approval | Partial. Temporary Certificate of Occupancy walk through for North portion of building. | |
| 08/27/2021 | BUILDING - PROGRESS | Partial Approval | Partial. TCO walk through for North half of project. | |
| 08/26/2021 | BUILDING - PROGRESS | Partial Approval | Partial. Room units, meters and room panels {02035): Building B, #4F House panel; Building D #200; 300; 545; Building G: 241, 242, 243, 244, 246, 641, 642, 643, 644, 646. Ok to energize meters and panels. CLEARANCE: Code: ECO |
|
| 08/25/2021 | BUILDING - PROGRESS | Not ready for Inspection | . Not ready. Contractor cancelled. Will reschedule for 26 August. | |
| 08/23/2021 | BUILDING - PROGRESS | Partial Approval | Partial. Information for TCO walk through 27 August. | |
| 08/06/2021 | BUILDING - PROGRESS | Partial Approval | Partial. Room finals at Levels #3, 4, 5, 6: Room units 303-311; 404-411; 505-511; 604-611. Exterior curb at Northeast corner of building to mid point of building: approximately 110’. |
|
| 07/27/2021 | BUILDING - PROGRESS | Partial Approval | Partial. Building C, Level #2; Room Units 204, 206, 208, 209, 210, 211: room final inspections. | |
| 07/21/2021 | BUILDING - PROGRESS | Partial Approval | Partial. Schedule for TCO walk through. | |
| 06/23/2021 | BUILDING - PROGRESS | Partial Approval | Partial. Sections A and B; Room Units, corridors, and common areas are complete. Construction in these areas has been completed | |
| 04/05/2021 | BUILDING - PROGRESS | Partial Approval | Partial. Complete Room Units on Level #4; 452; 453; 454; 455; 456; 457. Level #5 complete Room Units 552; 553; 555; 556; 557. | |
| 04/02/2021 | BUILDING - PROGRESS | Partial Approval | Partial. Building A-B; Apartments at L1: 150-157; L2: 250-257; L3: 350-357. Apartments are complete. | |
| 03/26/2021 | BUILDING - PROGRESS | Denied | Denied. No contact information, please call your inspector for further information to set up an inspection. Called main office, referred me to a superintendent, call number and left a message. | |
| 03/22/2021 | BUILDING - PROGRESS | Not ready for Inspection | Not ready. Contractor cancelled. | |
| 03/18/2021 | BUILDING - PROGRESS | Partial Approval | Partial. Level #2; Room Units; 252; 253; 254; 255; 255. Level #3; Room Units: 352; 353; 354; 355; 356; 357. Room Units are complete. | |
| 01/22/2021 | BUILDING - PROGRESS | Partial Approval | PARTIAL LEVEL #4 METER SETS 420, 421, 422, 423, 424, 425, 426, 427, 428, 430, 404, 409, 406, 411, 408, 415, 410, 417, 412, 419 OK TO ENERGIZE PANELS AND SET METERS. LEVEL #5 METER SETS 520, 521, 522, 523, 525, 524, 526, 527, 528, 530, 504, 509, 506, 611, 508, 515, 510, 517, 512, 519 OK TO ENERGIZE PANELS AND SET METERS. LEVEL #6 METER SETS 604, 623, 606, 625, 608, 624, 628, 626, 630, 627, 617, 609, 619, 610, 620, 611, 621, 612, 622, 615 OK TO ENERGIZE PANELS AND SET METERS. | |
| 01/20/2021 | BUILDING - PROGRESS | Not ready for Inspection | NOT READY, CONTRACTOR CANCELLED WILL RESCHEDULE FOR 21 JANUARY | |
| 12/31/2020 | BUILDING - PROGRESS | Partial Approval | Partial. Information only. Perimeter parapet wall construction requirements as per plan . Changes to be addressed by Building Official. | |
| 10/02/2020 | BUILDING - PROGRESS | Not ready for Inspection | Not Ready . Level #2; Section I Room Units 230 Line sets need to be set in place and insulated; 232 trades work incomplete. | |
| 08/14/2020 | BUILDING - PROGRESS | Partial Approval | Partial. Buildings H; I; G all at Level #2: Lag bolts at 12” and 48” on center. | |
| 08/13/2020 | BUILDING - PROGRESS | Cancelled | Canceled by contractor. | |
| 06/01/2020 | BUILDING - PROGRESS | Partial Approval | Partial. Level #5; Section I; sub floor. Ok to frame on progress areas. | |
| 05/28/2020 | BUILDING - PROGRESS | Partial Approval | Partial. Information only: inspection scheduling. | |
| 05/20/2020 | BUILDING - PROGRESS | Not ready for Inspection | Not ready. Contractor cancelled. | |
| 05/19/2020 | BUILDING - PROGRESS | Cancelled | ||
| 02/26/2020 | BUILDING - PROGRESS | Partial Approval | Information on fire caulking requirements. | |
| 10/31/2019 | BUILDING - PROGRESS | Partial Approval | Information only, plumbing for non ADA bathrooms. |