Permit: T17CM08216

Parcel: 11720016G


Addresses:

110 S CHURCH AV

Inspection Status: Approved

Inspection History: BUILDING - PROGRESS

Date Description Inspector Results Comments
12/27/2021 BUILDING - PROGRESS Approved Approved. Level #2; Units #221-228; 230-244; 246; 248. Level #1; Units; 122, 124, 126; 128; 130; 132.
12/23/2021 BUILDING - PROGRESS Partial Approval Partial. Level #3 Units: #321-328; 330-344; 346, 348. Appliances are in place.
12/21/2021 BUILDING - PROGRESS Partial Approval Partial. Level #4; Units: 421-428; 430-444: 446,448. Units are complete; appliances are in place.
12/20/2021 BUILDING - PROGRESS Not ready for Inspection Not ready. Level #4; ADA Units are not ready. Washer/dryer to be replaced.
12/16/2021 BUILDING - PROGRESS Partial Approval Partial. Level #5; Units 3521-528; 530-544; 546,548. Level #5 Room units are complete.
12/15/2021 BUILDING - PROGRESS Not ready for Inspection Not ready. Contractor cancelled. Will reschedule for 16 December.
12/14/2021 BUILDING - PROGRESS Not ready for Inspection Not ready. Contractor cancelled. All appliances are not in on Level #5. Will recall when in place.
12/13/2021 BUILDING - PROGRESS Partial Approval Partial. Level #6; Room Units: 621-629: 630-644; 646; 648. All appliances are in place; Room Units are complete.
11/04/2021 BUILDING - PROGRESS Partial Approval Partial. Electric meters for panels and room units: Section H, Level #1: 122,
124, 126, 128, 130, 132

CLEARANCE, Code: ECO
10/14/2021 BUILDING - PROGRESS Partial Approval Partial. Level #1; Section H-1, corridor and ceiling: all penetrations Fire stopped.
10/06/2021 BUILDING - PROGRESS Partial Approval Partial. Room finals in Sections E and F: Level #2 Rooms 212-220; Level #3 Rooms 312-320; Level #4 Rooms 412-420.
10/04/2021 BUILDING - PROGRESS Partial Approval Partial. Room finals in Sections C-D Level #5: 502-511; Level #6: 602-611; Sections E-F, Level 5, 502-511; Level #6, 612-620;
09/22/2021 BUILDING - PROGRESS Partial Approval Partial. Information for Temporary Certificate of Occupancy.
09/17/2021 BUILDING - PROGRESS Partial Approval Partial. ECO Meters and room panels to be energized: Section H, Level #1: 122, 124,126, 128, 130, 132. Section G, Level #2: 232, 240, 248. Section G, Level #3: 341, 342, 343, 344, 346, 348. Section G, Level #4: 441, 442, 443, 444, 446, 448. Section G, Level #5: 541, 542, 543, 544, 546, 548. Section D, Level #6: 602, 645. Section G, Level #6: 632, 639, 642, 648. Section I, Level #6: 631, 633, 634, 635, 636, 637, 638, 640.
09/15/2021 BUILDING - PROGRESS Partial Approval Partial. Information concerning access panels in level #2 of parking garage
09/10/2021 BUILDING - PROGRESS Partial Approval . Partial. Unit panels and meters: Section H, Level #1: 122, 124, 126, 128, 130, 132; Section G, Level #2: 232, 240, 248; Section G; Level #3: 341, 342, 343, 344, 346, 348; Section G, Level #4: 441, 442, 443, 444, 446, 448; Section G; Level #5: 541, 542, 543, 544, 546, 548; Section D, Level #6; 602, 645; Section G, Level #6; 632, 639, 642, 648; Section I, Level #6; 631, 633, 635, 637, 634, 636, 638, 64
08/31/2021 BUILDING - PROGRESS Partial Approval Partial. Temporary Certificate of Occupancy walk through for North portion of building.
08/27/2021 BUILDING - PROGRESS Partial Approval Partial. TCO walk through for North half of project.
08/26/2021 BUILDING - PROGRESS Partial Approval Partial. Room units, meters and room panels {02035): Building B, #4F House panel; Building D #200; 300; 545; Building G: 241, 242, 243, 244, 246, 641, 642, 643, 644, 646. Ok to energize meters and panels.

CLEARANCE: Code: ECO
08/25/2021 BUILDING - PROGRESS Not ready for Inspection . Not ready. Contractor cancelled. Will reschedule for 26 August.
08/23/2021 BUILDING - PROGRESS Partial Approval Partial. Information for TCO walk through 27 August.
08/06/2021 BUILDING - PROGRESS Partial Approval Partial. Room finals at Levels #3, 4, 5, 6: Room units 303-311; 404-411; 505-511; 604-611.

Exterior curb at Northeast corner of building to mid point of building: approximately 110’.
07/27/2021 BUILDING - PROGRESS Partial Approval Partial. Building C, Level #2; Room Units 204, 206, 208, 209, 210, 211: room final inspections.
07/21/2021 BUILDING - PROGRESS Partial Approval Partial. Schedule for TCO walk through.
06/23/2021 BUILDING - PROGRESS Partial Approval Partial. Sections A and B; Room Units, corridors, and common areas are complete. Construction in these areas has been completed
04/05/2021 BUILDING - PROGRESS Partial Approval Partial. Complete Room Units on Level #4; 452; 453; 454; 455; 456; 457. Level #5 complete Room Units 552; 553; 555; 556; 557.
04/02/2021 BUILDING - PROGRESS Partial Approval Partial. Building A-B; Apartments at L1: 150-157; L2: 250-257; L3: 350-357. Apartments are complete.
03/26/2021 BUILDING - PROGRESS Denied Denied. No contact information, please call your inspector for further information to set up an inspection. Called main office, referred me to a superintendent, call number and left a message.
03/22/2021 BUILDING - PROGRESS Not ready for Inspection Not ready. Contractor cancelled.
03/18/2021 BUILDING - PROGRESS Partial Approval Partial. Level #2; Room Units; 252; 253; 254; 255; 255. Level #3; Room Units: 352; 353; 354; 355; 356; 357. Room Units are complete.
01/22/2021 BUILDING - PROGRESS Partial Approval PARTIAL LEVEL #4 METER SETS 420, 421, 422, 423, 424, 425, 426, 427, 428, 430, 404, 409, 406, 411, 408, 415, 410, 417, 412, 419 OK TO ENERGIZE PANELS AND SET METERS. LEVEL #5 METER SETS 520, 521, 522, 523, 525, 524, 526, 527, 528, 530, 504, 509, 506, 611, 508, 515, 510, 517, 512, 519 OK TO ENERGIZE PANELS AND SET METERS. LEVEL #6 METER SETS 604, 623, 606, 625, 608, 624, 628, 626, 630, 627, 617, 609, 619, 610, 620, 611, 621, 612, 622, 615 OK TO ENERGIZE PANELS AND SET METERS.
01/20/2021 BUILDING - PROGRESS Not ready for Inspection NOT READY, CONTRACTOR CANCELLED WILL RESCHEDULE FOR 21 JANUARY
12/31/2020 BUILDING - PROGRESS Partial Approval Partial. Information only. Perimeter parapet wall construction requirements as per plan . Changes to be addressed by Building Official.
10/02/2020 BUILDING - PROGRESS Not ready for Inspection Not Ready . Level #2; Section I Room Units 230 Line sets need to be set in place and insulated; 232 trades work incomplete.
08/14/2020 BUILDING - PROGRESS Partial Approval Partial. Buildings H; I; G all at Level #2: Lag bolts at 12” and 48” on center.
08/13/2020 BUILDING - PROGRESS Cancelled Canceled by contractor.
06/01/2020 BUILDING - PROGRESS Partial Approval Partial. Level #5; Section I; sub floor. Ok to frame on progress areas.
05/28/2020 BUILDING - PROGRESS Partial Approval Partial. Information only: inspection scheduling.
05/20/2020 BUILDING - PROGRESS Not ready for Inspection Not ready. Contractor cancelled.
05/19/2020 BUILDING - PROGRESS Cancelled
02/26/2020 BUILDING - PROGRESS Partial Approval Information on fire caulking requirements.
10/31/2019 BUILDING - PROGRESS Partial Approval Information only, plumbing for non ADA bathrooms.