Inspection Status: Approved
Inspection History: BUILDING ABOVE CEILING
| Date |
Description |
Inspector |
Results |
Comments |
| 07/21/2021 |
BUILDING ABOVE CEILING |
|
Approved |
Approved |
| 10/13/2020 |
BUILDING ABOVE CEILING |
|
Not ready for Inspection |
Not ready, not complete. |
| 10/07/2020 |
BUILDING ABOVE CEILING |
|
Partial Approval |
Partial. Room Units 230; 232; 323; 324; 325; 326. |
| 09/11/2020 |
BUILDING ABOVE CEILING |
|
Partial Approval |
Partial. Level #6; Room Units #612 - 622 |
| 09/08/2020 |
BUILDING ABOVE CEILING |
|
Partial Approval |
Partial. Level #5; Room Units 517; 519; 520; 521. |
| 09/03/2020 |
BUILDING ABOVE CEILING |
|
Not ready for Inspection |
Not ready. Contractor cancelled. |
| 09/02/2020 |
BUILDING ABOVE CEILING |
|
Not ready for Inspection |
Not ready. Contractor cancelled will reschedule for 3 September |
| 08/26/2020 |
BUILDING ABOVE CEILING |
|
Partial Approval |
Partial. Level #4; Room Units 412; 415; 417; 421; 422. Ok to sheet rock throughout. |
| 08/10/2020 |
BUILDING ABOVE CEILING |
|
Not ready for Inspection |
Not ready. Contractor cancelled. |
| 07/31/2020 |
BUILDING ABOVE CEILING |
|
Partial Approval |
Partial. Building C; Level #2; Room Units #217; 219; 220; 221; 222 |
| 07/29/2020 |
BUILDING ABOVE CEILING |
|
Partial Approval |
Partial; Building C ; Level #6; Room Units #604; 606; 609; 610; 645. Building D; Level #2; Unit Rooms #212; 215. |
| 07/27/2020 |
BUILDING ABOVE CEILING |
|
Not ready for Inspection |
Not ready. Contractor cancelled. |
| 06/30/2020 |
BUILDING ABOVE CEILING |
|
Partial Approval |
Partial. Levels #2&3; Section corridors C & D |
| 06/23/2020 |
BUILDING ABOVE CEILING |
|
Not ready for Inspection |
Not ready. Contractor cancelled. |
| 06/22/2020 |
BUILDING ABOVE CEILING |
|
Not ready for Inspection |
Not ready. Contractor cancelled. |
| 06/17/2020 |
BUILDING ABOVE CEILING |
|
Not ready for Inspection |
Not ready. Contractor cancelled. |
| 06/08/2020 |
BUILDING ABOVE CEILING |
|
Not ready for Inspection |
Not ready, contractor cancelled. |
| 05/21/2020 |
BUILDING ABOVE CEILING |
|
Partial Approval |
Partial. Buildings C and D Unit Rooms #200; 202; 204; 206; 208; 209; 210; 211; 245. |
| 05/20/2020 |
BUILDING ABOVE CEILING |
|
Not ready for Inspection |
Not ready. Contractor cancelled. |
| 05/19/2020 |
BUILDING ABOVE CEILING |
|
Cancelled |
|
| 04/08/2020 |
BUILDING ABOVE CEILING |
|
Partial Approval |
RVI ROOM 650 |
| 03/13/2020 |
BUILDING ABOVE CEILING |
|
Partial Approval |
Levels #4; 5; 6 Sections A & B; above ceilings. Ok to cover progress areas. |
| 03/11/2020 |
BUILDING ABOVE CEILING |
|
Partial Approval |
Buildings A&B, corridors A&B, floors 2&3. |
| 02/25/2020 |
BUILDING ABOVE CEILING |
|
Partial Approval |
Level #2; Sections A & B; insulation above ceiling in apartments. Ok to cover. |