Permit: T17CM08216

Parcel: 11720016G


Addresses:

110 S CHURCH AV


Inspection Status: Approved

Inspection History: FRAMING

Permit Number - T17CM08216

Inspection Description - FRAMING

Inspection Status - Approved

Date Description Inspector Results Comments
07/21/2021 FRAMING Approved Approved
05/03/2021 FRAMING Partial Approval Partial. Level #6; Room Unit 642. Ok to insulate and cover walls.
03/26/2021 FRAMING Denied Denied. No contact information, please call your inspector for further information to set up an inspection. Called main office, referred me to a superintendent, call number and left a message.
03/16/2021 FRAMING Partial Approval Partial. Room Units on Level #6; 608; 628; 632. Ok to insulate and cover walls.
01/27/2021 FRAMING Partial Approval Partial. Level B-2; Room Units 122; 124; 126; 128; 130. Ensure all fire penetrations are properly caulked.
01/14/2021 FRAMING Partial Approval Partial. Level #3; Room Units meter sets; 304; 306; 308; 309; 310; 311; 312; 315; 317; 319; 320; 321; 322; 323; 324; 325; 326; 326; 327; 328; 330. OK to set meters for Room Units.
01/12/2021 FRAMING Partial Approval Partial. Theater roof line: ledger and ledger bolts in place at 12” on center.
01/11/2021 FRAMING Partial Approval Partial. Level #6; Room Units 641; 643; 644; 646; 648. Ok to insulate and cover walls.
12/23/2020 FRAMING Partial Approval Partial. Level #4; Room Units 441; 442; 443; 446; 448. Ok to insulate and cover walls.
12/18/2020 FRAMING Partial Approval Partial. Section H, Level #3; Room Units 341; 342; 343; 344; 346; 348. Level #6; Room Units 623; 625; 626; 627; 630. Ok to insulate and cover walls.
12/08/2020 FRAMING Partial Approval Partial. Level #2; Section G, Room Units 241; 243; 244; 246; 248. Level #5; Section H; Room Units 523; 524; 525; 526; 527; 528; 530; 532. Ok to insulate and cover walls.
12/07/2020 FRAMING Not ready for Inspection Not ready. Contractor cancelled, will reschedule for 8 December.
12/03/2020 FRAMING Partial Approval Partial. Level #1; Rooms 102; 104; 106; 108; 112. Ok to insulate and cover walls.
11/17/2020 FRAMING Partial Approval Partial. Level #5; Section I; Room Units 531-540. Ok to insulate and cover walls.
11/13/2020 FRAMING Not ready for Inspection Not ready. Contractor cancelled
10/23/2020 FRAMING Partial Approval Partial. Level #4; Section C; Room Units: 423; 424; 426; 427; 428; 430; 432. Ok to insulate and cover walls.
10/21/2020 FRAMING Partial Approval Partial. Level #3; Section H; Room Units 323; 324; 325; 326; 327; 328; 330; 332. Ok to insulate and cover walls.
10/20/2020 FRAMING Partial Approval Partial. Level #3; Room Units 331; 333; 334; 335; 336; 337; 338; 339; 340. Ok to cover walls.
10/16/2020 FRAMING Partial Approval Partial. Level #2; Section I; Room Units 231; 233; 234; 235; 236; 237; 238; 239; 240.
10/02/2020 FRAMING Partial Approval Partial. Level #2; Section I Room Units 223; 224; 225; 226; 227; 228. Ok to insulate and cover walls.
08/20/2020 FRAMING Not ready for Inspection Not ready. Contractor cancelled.
08/10/2020 FRAMING Partial Approval Partial.Level #6; Room Units #602 & 608. Elevator shafts #1 and #2. Ok to double layer sheet rock shafts.
07/21/2020 FRAMING Not ready for Inspection Not ready. Contractor cancelled. Will reschedule for 22 July
06/29/2020 FRAMING Not ready for Inspection Not ready. Contractor cancelled.
06/17/2020 FRAMING Not ready for Inspection Not ready. Contractor cancelled.
06/12/2020 FRAMING Not ready for Inspection Not ready. Contractor cancelled.
06/04/2020 FRAMING Not ready for Inspection Not ready. Contractor cancelled.
06/02/2020 FRAMING Not ready for Inspection Not ready. Contractor cancelled
06/01/2020 FRAMING Not ready for Inspection Not ready. Contractor cancelled.
05/28/2020 FRAMING Partial Approval Partial. Information for joist hangers and backing (RFI #382) and nailing pattern.
05/26/2020 FRAMING Not ready for Inspection Not ready. Contractor canceled.
05/21/2020 FRAMING Partial Approval Partial. Buildings C & D unit Rooms #200; 202; 204; 206 208; 209; 210; 211; 245.
04/24/2020 FRAMING Denied
04/15/2020 FRAMING Partial Approval RVI Level #4; Section H, sub flooring; Level #6; Sections E and F sub flooring. Ok to frame walls on sub floors.
04/06/2020 FRAMING Partial Approval RVI-Level #2 party walls in rooms: 200; 202; 204; 206; 208; 209; 210; 211; 245. Level #3 party walls in rooms: 300; 302; 304; 306; 308; 309; 310; 311; 345. Ok to insulate and cover walls in progress areas.
03/19/2020 FRAMING Not ready for Inspection Contractor cancelled.
03/18/2020 FRAMING Not ready for Inspection Not ready. Contractor cancelled
03/13/2020 FRAMING Not ready for Inspection Contractor cancelled.
03/11/2020 FRAMING Partial Approval Buildings A&B, corridors A&B, floors 2&3.
03/10/2020 FRAMING Partial Approval Level #1; Sections C & D North exterior walls. Ok to cover progress areas.
03/04/2020 FRAMING Partial Approval Levels #4 through #6; ATS System, all pins pulled, secured rods into place. Ok to cover.
03/02/2020 FRAMING Not ready for Inspection Contractor cancelled
02/28/2020 FRAMING Partial Approval Level #6; Buildings A & B, Rooms: 650; 652; 654; 655; 656; 657. Ok to insulate and cover walls.
02/05/2020 FRAMING Partial Approval Buildings A & B East exterior walls; dens-glas sheathing system. Ok to waterproof progress areas.
02/03/2020 FRAMING Not ready for Inspection Contractor cancelled
01/30/2020 FRAMING Partial Approval Section C, Level #5; sub-deck: West and South portions. Ok to frame walls in progress areas.
01/28/2020 FRAMING Not ready for Inspection Contractor cancelled
01/27/2020 FRAMING Not ready for Inspection Contractor cancelled.
01/24/2020 FRAMING Not ready for Inspection Contractor cancelled.
01/23/2020 FRAMING Partial Approval Section D; Level #5; sub deck. Ok to frame progress areas.
01/22/2020 FRAMING Not ready for Inspection Contractor cancelled.
01/09/2020 FRAMING Not ready for Inspection Rescheduled for 10 January early am.
01/02/2020 FRAMING Partial Approval Buildings A & B; Level #2; Rooms 250; 252; 253; 254; 255; 256; 257.
12/18/2019 FRAMING Not ready for Inspection Contractor cancelled due to heavy winds, unable to use crane.
12/17/2019 FRAMING Partial Approval Corridor ceilings on Levels #4; 5; 6. Ok to cover upper level of ceilings.
12/16/2019 FRAMING Not ready for Inspection Will reschedule 17 December, Contractor cancelled.
12/12/2019 FRAMING Partial Approval Levels 2; 3; 4 corridor ceilings: Ok to hang first layer of sheet rock.
12/09/2019 FRAMING Partial Approval Buildings A & B, Level #1 exterior walls. Ok to dens glass exterior walls.