Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit: T17CM08216

Parcel: 11720016G


Addresses:

110 S CHURCH AV


Inspection Status: Approved

Inspection History: BUILDING PRE-SLAB

Permit Number - T17CM08216

Inspection Description - BUILDING PRE-SLAB

Inspection Status - Approved

Date Description Inspector Results Comments
07/21/2021 BUILDING PRE-SLAB Approved Approved
06/03/2020 BUILDING PRE-SLAB Partial Approval Partial. Level #2; Section G; Post Tension Cable system. Ok to place concrete in progress areas.
05/11/2020 BUILDING PRE-SLAB Partial Approval Partial. Post Tension Cable System at GL: L/5-9; 6.6/H-J. Ok to place concrete in progress areas.
04/29/2020 BUILDING PRE-SLAB Partial Approval RVI Partial. (VRI). Garage Level #1 and Electric Room at GL: L/5.5-9. Electric conduits for outlets are in place. Area termite treated. Ok to place concrete in progress areas.
04/01/2020 BUILDING PRE-SLAB Partial Approval Ramp for parking garage, ground level to entrance of garage (ramp complete). GL:6.6-9/E.2-J. Ok to place concrete in progress areas.
RVI
03/24/2020 BUILDING PRE-SLAB Partial Approval Garage ramp at GL: 6.6/A-J; 9/A-J. Ok to place concrete in progress areas
03/20/2020 BUILDING PRE-SLAB Not ready for Inspection Contractor cancelled. Will reschedule for 23 March.
03/03/2020 BUILDING PRE-SLAB Partial Approval Level #2;Section H: Post Tension Cable System. Ok to place concrete in progress areas.
02/14/2020 BUILDING PRE-SLAB Partial Approval Post tension at first level south section OK.
02/05/2020 BUILDING PRE-SLAB Not ready for Inspection Contractor cancelled.
01/31/2020 BUILDING PRE-SLAB Not ready for Inspection Contractor cancelled. Sub-deck at Section C, Level #4 not ready.
01/30/2020 BUILDING PRE-SLAB Partial Approval Apron for Ramp I, Ok to place concrete.
01/22/2020 BUILDING PRE-SLAB Partial Approval Section E, Post Tension Cable System inspected 19 January. Ok to place concrete in progress areas.
12/31/2019 BUILDING PRE-SLAB Partial Approval Level #2; Section F, Post Tension Cable System. Ok to,place concrete in progress.
12/10/2019 BUILDING PRE-SLAB Partial Approval Post Tension Cable System at Level #2; Section E. Ok to place concrete in progress areas.
12/09/2019 BUILDING PRE-SLAB Not ready for Inspection Rained out. Reschedule for 10 December.
11/14/2019 BUILDING PRE-SLAB Partial Approval Level #2; slab area EP-2 at GL: A-E.3/4.2-6.6. Post Tension Cable System, Ok to place concrete in progress areas.
11/13/2019 BUILDING PRE-SLAB Partial Approval This inspection was performed on 12 November.
11/07/2019 BUILDING PRE-SLAB Partial Approval P-2 slab, Post Tension Cable System at GL: A/6.5-9; D/6.5-9. Ok to place concrete in progress areas.
10/30/2019 BUILDING PRE-SLAB Partial Approval Area E-1 slab at GL: 7/A.1-D; 4.3-7/D-A.1. Area F-2; Post Tension Cable System at GL: 5/E.4-H; H/4.6-6.6. Ok to place concrete in progress areas.
10/17/2019 BUILDING PRE-SLAB Partial Approval Slab at GL: C-H/4.6-7. Ok to place concrete. Grounding for IDF Room within this slab.
10/10/2019 BUILDING PRE-SLAB Not ready for Inspection This inspection was performed on 9 October.
10/09/2019 BUILDING PRE-SLAB Partial Approval Post Tension Cable system on Level #2; Section D. Ok to place concrete in progress areas.
09/27/2019 BUILDING PRE-SLAB Partial Approval Level #2; Section C: Electric and plumbing in place in the slab area. Ok to place concrete in progress areas.
09/23/2019 BUILDING PRE-SLAB Not ready for Inspection Discrepancy in PT plans. Need to submit corrections
09/18/2019 BUILDING PRE-SLAB Partial Approval Slab at Level #2; Section B; double meat rebar.
08/22/2019 BUILDING PRE-SLAB Partial Approval Section D-L2: Post Tension Cable System. Ok to place concrete.
08/19/2019 BUILDING PRE-SLAB Partial Approval Exterior wall at GL: A/5.5. Ok to place concrete in progress areas.
08/14/2019 BUILDING PRE-SLAB Partial Approval Post Tension cable system at Level #1; Section. "C". Ok to place concrete.
08/07/2019 BUILDING PRE-SLAB Not ready for Inspection too many different sets of drawings and too many revisions that are not up-to-date and stamped. Different drawings are saying different things. Issues with steps in the slab and the amount of bars and locations, issues with quantity of hairpins, issues with quantity of cables. Need the most up to date and current drawings on site and stamped and approved at time of inspection.
07/08/2019 BUILDING PRE-SLAB Partial Approval (P2 area D deck) ok to pour pending special inspectors report on post tension.
06/27/2019 BUILDING PRE-SLAB Partial Approval Section A. Ok to place concrete.
06/26/2019 BUILDING PRE-SLAB Partial Approval Post tension Pour C - L2 only
06/19/2019 BUILDING PRE-SLAB Partial Approval Slab and rebar in section H and stairwell number one.
06/12/2019 BUILDING PRE-SLAB Partial Approval 1- Steel reinforcement provided in columns located between grid line G to 9, H to 9 and J to 9.
2- Steel reinforcement mat for slab between grid lines 2,5 to 5 and H to 5. Is okay for concrete.
06/07/2019 BUILDING PRE-SLAB Partial Approval W3 & W1 walls
GL D.7, E.7 from 7.9-9.2
GL 7.9;9.2 from D.7-E.2
GL 9 from C.5-D.7
CC4 column C/5
05/03/2019 BUILDING PRE-SLAB Partial Approval CC2 Columns lower level area D and 5/F, 5/G & 5/E
04/18/2019 BUILDING PRE-SLAB Not ready for Inspection no work