Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit: T17CM08216

Parcel: 11720016G


Addresses:

110 S CHURCH AV


Inspection Status: Approved

Inspection History: STEM WALL/RETAINING WALL

Permit Number - T17CM08216

Inspection Description - STEM WALL/RETAINING WALL

Inspection Status - Approved

Date Description Inspector Results Comments
07/21/2021 STEM WALL/RETAINING WALL Approved Approved
11/04/2020 STEM WALL/RETAINING WALL Partial Approval Partial. Walk way at main entry at elevator area. Epoxy rebar placement and footings as per plans. Ok to place concrete in progress areas.
05/18/2020 STEM WALL/RETAINING WALL Partial Approval Partial. Stem walls at GL: 9/L. Ok to place concrete in progress areas.
04/30/2020 STEM WALL/RETAINING WALL Partial Approval Partial. Building A & B Southwest corner exterior steps at GL: aE/4.6-5.2
Retaining walls. Ok to place concrete in progress areas.
04/15/2020 STEM WALL/RETAINING WALL Not ready for Inspection RVI Contractor cancelled.
04/14/2020 STEM WALL/RETAINING WALL Partial Approval RVI Retaining wall at GL: L/5.3 at 12’5” to 17’3”. Ok to set framing and place concrete.
03/24/2020 STEM WALL/RETAINING WALL Partial Approval
03/20/2020 STEM WALL/RETAINING WALL Partial Approval Retaining wall footing at GL: 9/J-L; L/8-9. Ok to place concrete in progress area..
02/21/2020 STEM WALL/RETAINING WALL Partial Approval Section H level 1 south wall. Stair 3-H level 1
02/20/2020 STEM WALL/RETAINING WALL Partial Approval SECTION C; Level #2; W3 wall at GL: A.2 - B/11. Ok to place concrete in progress area.
02/19/2020 STEM WALL/RETAINING WALL Partial Approval Section H, Level #2; W3 wall at GL: 9. Ok to place concrete in progress area.
02/07/2020 STEM WALL/RETAINING WALL Partial Approval Retaining wall continuation; approximately 15’ at,GL: E.2/9. Stairwell #3 at Level #1-C2; GL: 8-9/E.-D.7. Ok to place concrete in progress areas.
02/05/2020 STEM WALL/RETAINING WALL Not ready for Inspection Contractor cancelled.
01/27/2020 STEM WALL/RETAINING WALL Partial Approval Retaining wall at GL: E.2/9.2-11; 11/A.1-E.2. Ok to place concrete in progress areas.
01/22/2020 STEM WALL/RETAINING WALL Partial Approval Retaining wall footing at GL: A-E.2/11; E.2/9; A.2/10.7. Ok to place concrete in progress area.
12/31/2019 STEM WALL/RETAINING WALL Not ready for Inspection Contractor cancelled.
12/19/2019 STEM WALL/RETAINING WALL Partial Approval Level #2; Elevator #3; Stairwell #4: shear walls. Ok to place concrete.
12/18/2019 STEM WALL/RETAINING WALL Not ready for Inspection Contractor cancelled due to heavy winds, unable to use crane.
12/16/2019 STEM WALL/RETAINING WALL Not ready for Inspection Will reschedule 17 December, Contractor cancelled.
12/12/2019 STEM WALL/RETAINING WALL Partial Approval Level #2; Section E, 14 concrete columns. Ok to set forms and place concrete
12/05/2019 STEM WALL/RETAINING WALL Partial Approval Section #8; stem walls at GL: A.2/9-10.8; 10.8/A.-E; E/9.2-10.8; walls at 6’2". Ok to place concrete in progress areas.
12/04/2019 STEM WALL/RETAINING WALL Not ready for Inspection Contractor cancelled; reschedule for 5 December.
12/03/2019 STEM WALL/RETAINING WALL Partial Approval Shear wall (W-3) at GL: 6.6/F-H. Ok to place concrete.
12/02/2019 STEM WALL/RETAINING WALL Partial Approval Concrete columns (5) at Level #1; Section F at GL: E/4.3; E.4/4.5; E/5; E/6; H/6. Ok to place concrete in progress areas.
11/26/2019 STEM WALL/RETAINING WALL Not ready for Inspection
11/19/2019 STEM WALL/RETAINING WALL Partial Approval Stairwell 3 and Elevator #4 walls. At Level P2.
11/12/2019 STEM WALL/RETAINING WALL Partial Approval Stem wall at GL: A.2-B/10.8; A/7-9. Ok to place concrete in progress areas.
11/06/2019 STEM WALL/RETAINING WALL Partial Approval Stem wall at GL: 6.6/F-H. Ok to place concrete.
11/04/2019 STEM WALL/RETAINING WALL Not ready for Inspection Contractor cancelled.
10/24/2019 STEM WALL/RETAINING WALL Partial Approval Lvl P-1 grid 6.5-5, F-D

Lvl P-1 grid 7-9, A-D

Ok to proceed
10/22/2019 STEM WALL/RETAINING WALL Partial Approval Partial. Stem wall at GL. 6.6/D-F at 18”-28”. Ok to form and place concrete
10/21/2019 STEM WALL/RETAINING WALL Partial Approval Stem wall at GL:6 approximately 40 feet. Ok to place concrete in progress area.
08/29/2019 STEM WALL/RETAINING WALL Not ready for Inspection Contractor cancelled.
08/28/2019 STEM WALL/RETAINING WALL Not ready for Inspection contractor cancelled.
08/26/2019 STEM WALL/RETAINING WALL Not ready for Inspection contractor cancelled
08/22/2019 STEM WALL/RETAINING WALL Partial Approval Section C-L2; Stairwell #1; exterior walls. Ok to place concrete in progress areas
08/21/2019 STEM WALL/RETAINING WALL Partial Approval Area B, W-5 stem wall at D.9/1.2-1.6. Ok to place concrete.
08/20/2019 STEM WALL/RETAINING WALL Partial Approval Section D stem walls at GL: a23; aD; aE, a24. Ok to place concrete in progress areas.
08/19/2019 STEM WALL/RETAINING WALL Partial Approval Exterior wall at GL: A/5.5. Ok to place concrete in progress areas.
08/16/2019 STEM WALL/RETAINING WALL Partial Approval Stem walls at GL: aB-aD/a23; aD/a23-a24. Ok to place concrete in progress areas.
08/15/2019 STEM WALL/RETAINING WALL Partial Approval Section “B”; big wall at A21-A23/aA; small wall at A2-Ae. Ok to place concrete in progress areas.
08/14/2019 STEM WALL/RETAINING WALL Partial Approval F11/W2 footing at GL: A/4.1/5.5. Ok to place concrete .
08/09/2019 STEM WALL/RETAINING WALL Partial Approval this was an on-site meeting to discuss the changes and revisions that are not aligning with the permitted and approved set of drawings. We are now awaiting on either the engineers approval on some conflicting issues in order to pour level 1 deck or work needs to be fixed to reflect the approved drawings.
08/08/2019 STEM WALL/RETAINING WALL Partial Approval retaining wall section D level one E. side OK to pour.
08/07/2019 STEM WALL/RETAINING WALL Not ready for Inspection too many different sets of drawings and too many revisions that are not up-to-date and stamped. Different drawings are saying different things. Issues with steps in the slab and the amount of bars and locations, issues with quantity of hairpins, issues with quantity of cables. Need the most up to date and current drawings on site and stamped and approved at time of inspection.
08/05/2019 STEM WALL/RETAINING WALL Partial Approval 1- Steel reinforcement is okay for the Stairwell 1 and Elevators 1 & 2 level P2 to level 1 only.
07/22/2019 STEM WALL/RETAINING WALL Partial Approval Gridline D9 retaining portion of Level 1 ok (take photos of North west corner after bars are epoxied). Section Z4 of wall on level one ok (straighten up vertical rebar at column so spacing is 4 inches at bottom and at top, take photo of fix).
07/18/2019 STEM WALL/RETAINING WALL Partial Approval OK to pour walls on level one sections C and D. Need detail stamped from the engineer showing that keyway is not needed and that number fours tying walls into columns are OK.
07/15/2019 STEM WALL/RETAINING WALL Partial Approval 1- Steel reinforcement okay in wall C level P2.
07/10/2019 STEM WALL/RETAINING WALL Not ready for Inspection Contractor cancelled.
07/02/2019 STEM WALL/RETAINING WALL Not ready for Inspection canceled
07/01/2019 STEM WALL/RETAINING WALL Not ready for Inspection Did not pass special inspections
06/26/2019 STEM WALL/RETAINING WALL Partial Approval Post tension Pour C - L2 only
06/25/2019 STEM WALL/RETAINING WALL Partial Approval W3 wall GL 9 from B-C.9
06/24/2019 STEM WALL/RETAINING WALL Not ready for Inspection AREA H INCOMPLETE
06/19/2019 STEM WALL/RETAINING WALL Partial Approval Section I line 9 columns F through H
06/12/2019 STEM WALL/RETAINING WALL Partial Approval 1- Steel reinforcement provided in columns located between grid line G to 9, H to 9 and J to 9.
2- Steel reinforcement mat for slab between grid lines 2,5 to 5 and H to 5. Is okay for concrete.
06/10/2019 STEM WALL/RETAINING WALL Partial Approval Level P1 Areas C & D
GL 1-2.5 from E.35-L.4
06/06/2019 STEM WALL/RETAINING WALL Partial Approval Level P1 Area D only floor drain to sump pump only
06/03/2019 STEM WALL/RETAINING WALL Partial Approval W1 wall GL 6.6 from G-F only
W2 wall stairwell 1 level 1 only
05/31/2019 STEM WALL/RETAINING WALL Partial Approval 1- Steel reinforcement provided in columns located between grid lines 6.6 to grid line F and between grid line D to 5- 4.5 and between C to grid line 4.5 all 9.2 inches AFF only.
05/30/2019 STEM WALL/RETAINING WALL Partial Approval 1- Steel reinforcement provided in stem wall between column Z4 to 4.1 and between YC to X11 only.
05/24/2019 STEM WALL/RETAINING WALL Partial Approval W3 wall GL AE from A9-A11
05/23/2019 STEM WALL/RETAINING WALL Partial Approval CC2 columns GL AE/A9 & AE/A11
05/22/2019 STEM WALL/RETAINING WALL Not ready for Inspection no work
05/21/2019 STEM WALL/RETAINING WALL Partial Approval W9 wall GL F1 from 1.8-2
W1 wall GL H.3 from 5.5-6.6
W1 wall GL H.3 from G-J
05/20/2019 STEM WALL/RETAINING WALL Partial Approval Wall footing on Gridline F 1.8 to 2 ok. Retaining wall 1st parking level gridline Z2 from X5 to G8 ok.
05/17/2019 STEM WALL/RETAINING WALL Not ready for Inspection canceled
05/16/2019 STEM WALL/RETAINING WALL Partial Approval W3 wall level P1 GL Z2 from X2- X5 only
05/15/2019 STEM WALL/RETAINING WALL Partial Approval Per detail 231 GL 5.5 from J-M
05/14/2019 STEM WALL/RETAINING WALL Partial Approval W3 walls GL X11 from Z2-Z4
W3 walls GL Z2 from X5-X11
Except #4 dowels epoxy column X8 special inspection
Except weld plates 6” wall see highlighted S1.1 plan
05/13/2019 STEM WALL/RETAINING WALL Partial Approval elevator one and two pit walls only
05/10/2019 STEM WALL/RETAINING WALL Not ready for Inspection Not ready. Not complete
05/09/2019 STEM WALL/RETAINING WALL Partial Approval Steel reinforcement provided for the wall located at 5.2 H3 to L only 2- Steel reinforcement provided in column H- 1.6 only.
05/08/2019 STEM WALL/RETAINING WALL Partial Approval RFI change number 218. Line H columns on Row 2,3,&4.
04/30/2019 STEM WALL/RETAINING WALL Partial Approval 20 each CC2 columns level p1 areas C&D
See highlighted s1.1 plan
04/29/2019 STEM WALL/RETAINING WALL Partial Approval CC2 Columns level P 1 GL 10.1/ A.3, B. B.8, C.9 & D.9
GL 10/ A.3, B, C, D & D.9
04/26/2019 STEM WALL/RETAINING WALL Partial Approval Trash room L1 to L2, W-2 wall type.
04/23/2019 STEM WALL/RETAINING WALL Partial Approval W3 wall GL ah from a21-a23
Column a14/aj
04/19/2019 STEM WALL/RETAINING WALL Partial Approval W3 walls GL am from a7- a1
GL a1 from an-we
GL we from a1-a2
04/18/2019 STEM WALL/RETAINING WALL Partial Approval CC2 columns AJ/A1, AH/A1, A14/ AE, & A16/ AG
04/17/2019 STEM WALL/RETAINING WALL Partial Approval W3 wall GL AA from A17- A21
W3 wall GL Aa from A7.5-A10 & GL A6 from AA-AE
04/11/2019 STEM WALL/RETAINING WALL Partial Approval Gridline AA section A17 to A7 (W3 wall type) ok except epoxied bar into columns on either end and except 16’ of stem wall at A8
04/09/2019 STEM WALL/RETAINING WALL Partial Approval stem wall on area A from line A3 to A13 on AJ ok, need to epoxy new bar going into existing wall where corner bars didn’t line up, make sure the special inspector sees and documents this and take photos.
04/02/2019 STEM WALL/RETAINING WALL Partial Approval East trash chute w-3 wall
03/28/2019 STEM WALL/RETAINING WALL Partial Approval Great check north stairwell and a previous five columns for clearance
03/27/2019 STEM WALL/RETAINING WALL Partial Approval Columns AA/A10, AA/A12, AD/A18, AD/A20 & AD/ A22
03/26/2019 STEM WALL/RETAINING WALL Partial Approval Columns lower level AA/A7, AI/A5, AI/A11, AI/A8, AF/A1
W5&W2 walls at stairwell 5 only