Inspection Status: Approved
Inspection History: FIRE SPKLR - FINAL
| Date |
Description |
Inspector |
Results |
Comments |
| 02/14/2020 |
FIRE SPKLR - FINAL |
|
Approved |
|
| 11/07/2019 |
FIRE SPKLR - FINAL |
|
Partial Approval |
Partial by CB on the 4th of November. Needs heads added to the tire storage rack |
| 05/08/2019 |
FIRE SPKLR - FINAL |
|
Compliance |
Need to add in-rack sprinkler coverage per MAB. Racks are 72" wide also look at the double 48" racks with possible hard lids |
| 01/18/2019 |
FIRE SPKLR - FINAL |
|
Partial Approval |
Okay for TCO on the first phase North side of building. |