Inspection History Details
Inspection Status: Approved
Inspection History: EXCAVATION/LAYOUT REBAR & ZON
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/25/2019 | EXCAVATION/LAYOUT REBAR & ZON | Approved | ||
| 10/17/2019 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | South Outdoor Showroom to awning. | |
| 10/15/2019 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | Exterior showroom from H-G. 2.5-5. Builder to obtain sealed change and submit to office. | |
| 03/20/2019 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | Light poles at north parking lot (6); and 3 light poles east of Kia sales. Elevator shaft walls, forms and steel. |
|
| 03/12/2019 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | Balance of building footings; still need to look at light pole bases. | |
| 03/08/2019 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | From grid lines D through F and 2.5 to 5 | |
| 06/08/2018 | EXCAVATION/LAYOUT REBAR & ZON | Denied | IVRS - Inspection : See detailed listing on site.| 999 1- JOB SITE TRAILER CLOSED AND NO ONE ON SITE. * |
|
| 05/07/2018 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | PA APPROVAL UNTIL ALL UNDER GROUND AND RE BAR IS COMPLETE ON WEST PARKING LOT |