Permit: T17CM07583

Parcel: 11507307B

Inspection Status: Approved

Inspection History: FIRE SPKLR - FINAL

Date Description Inspector Results Comments
07/31/2019 FIRE SPKLR - FINAL Approved
07/03/2019 FIRE SPKLR - FINAL Partial Approval Need to move the lights and or adjust the fire sprinkler heads in 5 units due to light fixture and obstruction rules
gaps next to escutcheons need to be patched
Bldg 2 needs the riser room to have a 3' clearance around the riser
03/04/2019 FIRE SPKLR - FINAL Partial Approval 207 & 209 PSI on the gauges. The west building design has completely been altered since the plans that we approved were issued with a permit. Need to have ASBUILT drawings prior to final. Some of the pipe is right on the heat registers need to move away. Three-Four heads were covered in foam and need to be replaced.
10/26/2017 FIRE SPKLR - FINAL Prior to Intermediates P2I MAY BE DELETED WHEN ROOF/FLOOR TRUSS DESIGN CALCULATIONS AND DRAWINGS HAVE BEEN REVIEWED AND APPROVED.