Inspection History Details
Inspection Status: Approved
Inspection History: FIRE SPKLR - FINAL
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 07/31/2019 | FIRE SPKLR - FINAL | Approved | ||
| 07/03/2019 | FIRE SPKLR - FINAL | Partial Approval | Need to move the lights and or adjust the fire sprinkler heads in 5 units due to light fixture and obstruction rules gaps next to escutcheons need to be patched Bldg 2 needs the riser room to have a 3' clearance around the riser |
|
| 03/04/2019 | FIRE SPKLR - FINAL | Partial Approval | 207 & 209 PSI on the gauges. The west building design has completely been altered since the plans that we approved were issued with a permit. Need to have ASBUILT drawings prior to final. Some of the pipe is right on the heat registers need to move away. Three-Four heads were covered in foam and need to be replaced. | |
| 10/26/2017 | FIRE SPKLR - FINAL | Prior to Intermediates | P2I MAY BE DELETED WHEN ROOF/FLOOR TRUSS DESIGN CALCULATIONS AND DRAWINGS HAVE BEEN REVIEWED AND APPROVED. |