Inspection Status: Approved
Inspection History: MECHANICAL - ABOVE CEILING
| Date |
Description |
Inspector |
Results |
Comments |
| 07/26/2019 |
MECHANICAL - ABOVE CEILING |
|
Approved |
|
| 04/09/2019 |
MECHANICAL - ABOVE CEILING |
|
Partial Approval |
1- Above ceiling is Okay to cover in bldg 2, 1st and 2nd floors only |
| 04/05/2019 |
MECHANICAL - ABOVE CEILING |
|
Partial Approval |
Rooms on levels #1 & #2. Ok to cover progress areas |
| 03/27/2019 |
MECHANICAL - ABOVE CEILING |
|
Partial Approval |
One, floors one and two |
| 03/25/2019 |
MECHANICAL - ABOVE CEILING |
|
Partial Approval |
Corridors |
| 03/22/2019 |
MECHANICAL - ABOVE CEILING |
|
Cancelled |
canceled by contractor |
| 03/06/2019 |
MECHANICAL - ABOVE CEILING |
|
Partial Approval |
All above heartland area in community center |