Inspection History Details
Inspection Status: Approved
Inspection History: EXT METAL CLIPS/EXT SHEATHING
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 03/27/2019 | EXT METAL CLIPS/EXT SHEATHING | Approved | ||
| 03/25/2019 | EXT METAL CLIPS/EXT SHEATHING | Cancelled | Need Ernie to verify completeness. | |
| 03/22/2019 | EXT METAL CLIPS/EXT SHEATHING | Cancelled | canceled by contractor | |
| 03/08/2019 | EXT METAL CLIPS/EXT SHEATHING | Not ready for Inspection | Missing anchor bolts on interior firewall | |
| 02/28/2019 | EXT METAL CLIPS/EXT SHEATHING | Partial Approval | Missing anchor bolts on sheer walls first floor | |
| 01/25/2019 | EXT METAL CLIPS/EXT SHEATHING | Partial Approval | This inspection should not be approved, it should be a partial (prior inspection changed upon these notes) |
|
| 01/16/2019 | EXT METAL CLIPS/EXT SHEATHING | Partial Approval | both east and west buildings | |
| 12/18/2018 | EXT METAL CLIPS/EXT SHEATHING | Partial Approval | 1- attended a walk through on the first bldg. with the Superintendent in reference to the installation of pre fab shear wall panels. |