Inspection Status: Approved
Inspection History: REINFORCED MASONRY PRE-GROUT
| Date |
Description |
Inspector |
Results |
Comments |
| 10/26/2018 |
REINFORCED MASONRY PRE-GROUT |
|
Approved |
Top out, 35’ elevator, 30’ stairs. |
| 10/25/2018 |
REINFORCED MASONRY PRE-GROUT |
|
Partial Approval |
Sixth lift, stairwell 20 feet to 27 feet with the cleanouts no bond beams. Elevator 20 feet to 30 feet with cleanouts, no bond beams |
| 10/23/2018 |
REINFORCED MASONRY PRE-GROUT |
|
Partial Approval |
Fifth lift, 14’8 to 20 feet |
| 10/22/2018 |
REINFORCED MASONRY PRE-GROUT |
|
Partial Approval |
Fourth lift 7’8 to 14’8 |
| 10/19/2018 |
REINFORCED MASONRY PRE-GROUT |
|
Partial Approval |
OK up to 10’8” with conforma-tech report |
| 10/17/2018 |
REINFORCED MASONRY PRE-GROUT |
|
Partial Approval |
Ok to grout elevator to 4'8" and stairs to 7'8" |
| 10/15/2018 |
REINFORCED MASONRY PRE-GROUT |
|
Cancelled |
Canceled by contractor |
| 10/12/2018 |
REINFORCED MASONRY PRE-GROUT |
|
Partial Approval |
Elevator and stair well, first lift 0 to5 feet |