Permit: T17CM07583

Parcel: 11507307B

Inspection Status: Approved

Inspection History: EXCAVATION/LAYOUT REBAR & ZON

Date Description Inspector Results Comments
03/06/2019 EXCAVATION/LAYOUT REBAR & ZON Approved
02/22/2019 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection 1- Trenches and footings had water due to snow and rain.
02/19/2019 EXCAVATION/LAYOUT REBAR & ZON Partial Approval North side wall footing
02/15/2019 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection not complete enough
01/25/2019 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection not complete enough
11/02/2018 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Building footings (East and West). Ok to place concrete
10/10/2018 EXCAVATION/LAYOUT REBAR & ZON Partial Approval Perimeter exterior wall and stairwell
10/08/2018 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection no steel and no completed forms please call when ready
10/04/2018 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection COMPLETE STEEL INSTALL AND RECALL
09/27/2018 EXCAVATION/LAYOUT REBAR & ZON Partial Approval That is a PA for elevator pit bottom only
07/19/2018 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :* EAST AND SOUTH FOOTINGS 10" X 24" FOR PERIMITER WALL