Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Inspection History Details
Inspection Status: Approved
Inspection History: BUILDING - PROGRESS
Permit Number - T17CM04982
Inspection Description - BUILDING - PROGRESS
Inspection Status - Approved
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 06/22/2020 | BUILDING - PROGRESS | Approved | Approved | |
| 06/17/2020 | BUILDING - PROGRESS | Partial Approval | Partial. Pre-Certificate of Occupancy walk through. Will call for Final on 22 June. | |
| 05/29/2020 | BUILDING - PROGRESS | Partial Approval | Partial. Information for possible “occupancy “ in name only, under current TCO. Referred to A. Quiroz for disposition. | |
| 05/28/2020 | BUILDING - PROGRESS | Partial Approval | Partial. Level #1; Electric room finals, Rooms: D; G; Amenities Room. | |
| 05/27/2020 | BUILDING - PROGRESS | Partial Approval | Partial. Level #1; Room units #102; 104; 106: electric complete. | |
| 05/26/2020 | BUILDING - PROGRESS | Partial Approval | Partial. Steps, benches, planters (01005) in courtyard center section. Ok to place concrete. | |
| 05/01/2020 | BUILDING - PROGRESS | Partial Approval | ||
| 04/29/2020 | BUILDING - PROGRESS | Partial Approval | RVI Partial. (VRI). Information only. | |
| 04/28/2020 | BUILDING - PROGRESS | Not ready for Inspection | Not ready. Level #6 unit rooms will be ready for Electric Finals on 29 April. | |
| 04/27/2020 | BUILDING - PROGRESS | Partial Approval | Partial. Set schedule for room electric final inspections on Level #6. | |
| 04/24/2020 | BUILDING - PROGRESS | Denied | 1- There was no contact number given on the inspection request. Please provide a contact number of the person who will be performing the video inspection at the time inspection request. I spoke with the office today at (480) 222-9103 and asked to contacted today before 3:00 pm. | |
| 04/23/2020 | BUILDING - PROGRESS | Partial Approval | ||
| 04/22/2020 | BUILDING - PROGRESS | Partial Approval | RVI Schedule for meter sets | |
| 04/21/2020 | BUILDING - PROGRESS | Partial Approval | (VRI). 02036. Level #1; Lobby area and mail room; canned lighting system. | |
| 04/20/2020 | BUILDING - PROGRESS | Partial Approval | ||
| 04/15/2020 | BUILDING - PROGRESS | Partial Approval | RVI Stairwell #3 sheetrock | |
| 04/14/2020 | BUILDING - PROGRESS | Not ready for Inspection | Contractor cancelled, will reschedule for 15 April | |
| 04/13/2020 | BUILDING - PROGRESS | Partial Approval | RVI-SET SCHEDULE FOR ROOM INSPECTIONS | |
| 04/10/2020 | BUILDING - PROGRESS | Partial Approval | RVI Interior courtyard planters. Reference RFI #352. | |
| 04/09/2020 | BUILDING - PROGRESS | Partial Approval | Set schedule for room final inspections. | |
| 04/08/2020 | BUILDING - PROGRESS | Partial Approval | VRI | |
| 04/07/2020 | BUILDING - PROGRESS | Not ready for Inspection | Contractor cancelled | |
| 04/06/2020 | BUILDING - PROGRESS | Not ready for Inspection | RVI-Contractor cancelled; will reschedule for 8 April. | |
| 04/03/2020 | BUILDING - PROGRESS | Partial Approval | (RVI). (01005). Patch and repair stem walls at South area; Southeast area; Southwest corner area. Ok to place concrete in progress areas. | |
| 04/02/2020 | BUILDING - PROGRESS | Not ready for Inspection | will reschedule for 3 April. | |
| 04/01/2020 | BUILDING - PROGRESS | Partial Approval | Setting up for Face Time | |
| 03/31/2020 | BUILDING - PROGRESS | Partial Approval | ||
| 03/27/2020 | BUILDING - PROGRESS | Cancelled | Canceled by contractor. | |
| 03/26/2020 | BUILDING - PROGRESS | Partial Approval | Level #1; Shower pans in units #102; 104; 106; 116; 118. | |
| 03/25/2020 | BUILDING - PROGRESS | Partial Approval | Trash chutes at Levels #1-6; (01044). Ok to cover walls to be rated at two hours. | |
| 03/11/2020 | BUILDING - PROGRESS | Cancelled | Canceled by contractor. | |
| 03/09/2020 | BUILDING - PROGRESS | Partial Approval | Information only. | |
| 03/06/2020 | BUILDING - PROGRESS | Partial Approval | Information only. 03005. Partial. Level #1; Public Restrooms: 1/2" domestic water, 2" waste. Ok to cover progress areas. 03035. Partial. Level #6; Unit shower pans: 611; 612; 614; 616; 618; 619. | |
| 03/05/2020 | BUILDING - PROGRESS | Partial Approval | (02036) Canned lighting system in North amenities area. Ok to cover ceiling. | |
| 03/03/2020 | BUILDING - PROGRESS | Partial Approval | Information only. | |
| 03/02/2020 | BUILDING - PROGRESS | Partial Approval | Information for electric inspection scheduling. | |
| 02/28/2020 | BUILDING - PROGRESS | Not ready for Inspection | Will reschedule for 2 March. | |
| 02/27/2020 | BUILDING - PROGRESS | Not ready for Inspection | Contractor cancelled. | |
| 02/26/2020 | BUILDING - PROGRESS | Partial Approval | Information only; set inspection schedule for room inspections. | |
| 02/25/2020 | BUILDING - PROGRESS | Partial Approval | Information concerning the location of exit lighting in basement maintenance rooms and lobby area. | |
| 02/21/2020 | BUILDING - PROGRESS | Cancelled | Canceled by contractor | |
| 02/20/2020 | BUILDING - PROGRESS | Partial Approval | (01044); Room #102E, trash chute, Fire caulked. (01036); grid ceiling system in Rooms: D and G. Ok to set ceiling tiles. | |
| 02/19/2020 | BUILDING - PROGRESS | Not ready for Inspection | Contractor cancelled. | |
| 02/18/2020 | BUILDING - PROGRESS | Partial Approval | Information only. Need electric panel information for TEP. | |
| 02/14/2020 | BUILDING - PROGRESS | Cancelled | Canceled by contractor | |
| 02/13/2020 | BUILDING - PROGRESS | Partial Approval | 01045- Level #1; Section B Corridor; Rooms: 104; 106. Ok to tape progress areas. | |
| 02/12/2020 | BUILDING - PROGRESS | Not ready for Inspection | Contractor cancelled. | |
| 02/11/2020 | BUILDING - PROGRESS | Not ready for Inspection | (01045); will reschedule for 12 February. | |
| 02/07/2020 | BUILDING - PROGRESS | Not ready for Inspection | no inspections ready at this time. | |
| 02/06/2020 | BUILDING - PROGRESS | Not ready for Inspection | Contractor cancelled. | |
| 02/05/2020 | BUILDING - PROGRESS | Partial Approval | Information only. Recommended fire safety construction for trash chutes on Levels 1 - 6. | |
| 02/04/2020 | BUILDING - PROGRESS | Partial Approval | (01045); Level #6; Corridor B; Rooms: 605; 606; 608. Ok to tape progress areas | |
| 02/03/2020 | BUILDING - PROGRESS | Partial Approval | Set electric schedule | |
| 01/31/2020 | BUILDING - PROGRESS | Partial Approval | Information only; set electric meter inspection schedule. | |
| 01/30/2020 | BUILDING - PROGRESS | Partial Approval | Electric intermediate: clearance to energize meter #LS1G and meter #Fire Pump. Information called in to Martin Rodriguez. | |
| 01/29/2020 | BUILDING - PROGRESS | Not ready for Inspection | Contractor cancelled. | |
| 01/28/2020 | BUILDING - PROGRESS | Partial Approval | Information only: reconfiguration of trash chute. | |
| 01/27/2020 | BUILDING - PROGRESS | Partial Approval | (01045): Level #6; Section A, corridor walls and ceilings, (from Rooms 612-619). Ok to tape progress areas. Level #6 Rooms; 601; 602; 604; 625. Ok to tape progress areas. | |
| 01/24/2020 | BUILDING - PROGRESS | Partial Approval | (02035); SES electric system at Level #1: Buss ducts, switch boards, disconnects. Panel #1L1A. Ok to energize SES System. Clearance: Code: ECO |
|
| 01/23/2020 | BUILDING - PROGRESS | Partial Approval | Sheetrock nailing on Levels #4 & 5 (corridors and ceilings); Level #6; Rooms 611; 613; 614; 615; 616; 617; 619. Ok to tape progress areas. | |
| 01/17/2020 | BUILDING - PROGRESS | Not ready for Inspection | will reschedule for 14 January. | |
| 01/16/2020 | BUILDING - PROGRESS | Not ready for Inspection | ||
| 01/15/2020 | BUILDING - PROGRESS | Partial Approval | Information only. Electric tie-in, grounding for panels and SES. | |
| 01/14/2020 | BUILDING - PROGRESS | Partial Approval | Level #4; Section B, fire caulking in and around mechanical unit areas in rooms. | |
| 01/13/2020 | BUILDING - PROGRESS | Partial Approval | Mechanical above ceiling; Level #4; Section A; HVAC units in rooms. Ok to cover. | |
| 01/10/2020 | BUILDING - PROGRESS | Partial Approval | 02036; South and Southeast canopy area; canned lighting in place. Ok to cover progress areas. | |
| 01/09/2020 | BUILDING - PROGRESS | Not ready for Inspection | Contractor cancelled. | |
| 01/08/2020 | BUILDING - PROGRESS | Not ready for Inspection | Contractor cancelled. Schedule rooms for 9 January. | |
| 01/07/2020 | BUILDING - PROGRESS | Not ready for Inspection | Contractor cancelled; rescheduled for 8 January | |
| 01/06/2020 | BUILDING - PROGRESS | Partial Approval | Information only; determined proposed electric cabinet and panel inspection schedule. | |
| 01/03/2020 | BUILDING - PROGRESS | Partial Approval | ||
| 01/02/2020 | BUILDING - PROGRESS | Not ready for Inspection | (01045). Will reschedule for 3 January | |
| 12/31/2019 | BUILDING - PROGRESS | Partial Approval | (01045). Level #5; Rooms 501; 502; 504; 505; 506; 511; 512; 513. Ok to tape progress areas. | |
| 12/20/2019 | BUILDING - PROGRESS | Not ready for Inspection | Soffit placement not ready | |
| 12/19/2019 | BUILDING - PROGRESS | Partial Approval | Framing; Truss space bearing for ATS base plates as per RFI #307, dated 12-12-19. Level #4 ATS locations in corridors and rooms. | |
| 12/18/2019 | BUILDING - PROGRESS | Partial Approval | Electrical information for kitchen island outlet placement. | |
| 12/17/2019 | BUILDING - PROGRESS | Partial Approval | 01045; Level #5; Rooms 514; 515; 516; 517; 518. Ok to tape progress areas. | |
| 12/16/2019 | BUILDING - PROGRESS | Not ready for Inspection | (01045), reschedule for 17 December | |
| 12/13/2019 | BUILDING - PROGRESS | Partial Approval | Level #6; Room 603 Mechanical, Electrical, Plumbing intermediates. Ok to insulate and cover walls. | |
| 12/12/2019 | BUILDING - PROGRESS | Partial Approval | (01035). Bearing truss space for ATS base plates; RFI #307 dated 12-12-19. Levels #3 and #5 corrections completed. | |
| 12/11/2019 | BUILDING - PROGRESS | Partial Approval | (01045). Level #2: Mechanical Ceilings in rooms: 212; 214; 215; 216; 218; 219. Ok to tape progress areas. Level #4; Rooms: 401; 407; 408; 409; 410. Ok to tape progress areas. | |
| 12/10/2019 | BUILDING - PROGRESS | Partial Approval | Electric, Plumbing, Mechanical above ceiling corridors A & B on level #6. Ok to cover ceilings. | |
| 12/09/2019 | BUILDING - PROGRESS | Partial Approval | (01045). Level #3; Room 301; Corridor A - double layer. Level #4; Room 406. Ok to tape progress areas. | |
| 12/06/2019 | BUILDING - PROGRESS | Partial Approval | Proposed new wiring system for room mechanical units. | |
| 12/05/2019 | BUILDING - PROGRESS | Partial Approval | (01045). Level #4; Rooms: 404; 405; 413; 418. Ok to tape progress areas. | |
| 12/04/2019 | BUILDING - PROGRESS | Partial Approval | (01045). Level #3; Corridor B. Level #4; Rooms : 402; 411; 411; 412; 414. Ok to tape progress areas. | |
| 12/02/2019 | BUILDING - PROGRESS | Partial Approval | Electric intermediate, electric service and devices inspected (courtesy inspection) by Dan Santa Cruz. | |
| 11/29/2019 | BUILDING - PROGRESS | Cancelled | Gates locked. | |
| 11/27/2019 | BUILDING - PROGRESS | Partial Approval | Level #6; Sections A & B: all apartments except for #604; Electric intermediate and above ceiling; mechanical intermediate and above ceiling. Ok to insulate and Sheetrock progress areas. | |
| 11/26/2019 | BUILDING - PROGRESS | Not ready for Inspection | Will reschedule for 27 November | |
| 11/25/2019 | BUILDING - PROGRESS | Not ready for Inspection | Contractor cancelled. | |
| 11/22/2019 | BUILDING - PROGRESS | Partial Approval | (01045). Level #3; Rooms: 307; 308; 310. Ok to tape progress areas. | |
| 11/21/2019 | BUILDING - PROGRESS | Partial Approval | ||
| 11/20/2019 | BUILDING - PROGRESS | Partial Approval | ||
| 11/19/2019 | BUILDING - PROGRESS | Not ready for Inspection | Rained out. Reschedule for 20 November | |
| 11/18/2019 | BUILDING - PROGRESS | Not ready for Inspection | Will reschedule for 19 November. | |
| 11/15/2019 | BUILDING - PROGRESS | Partial Approval | ||
| 11/14/2019 | BUILDING - PROGRESS | Partial Approval | ||
| 11/13/2019 | BUILDING - PROGRESS | Not ready for Inspection | Contractor cancelled. Will reschedule for 14 November | |
| 11/08/2019 | BUILDING - PROGRESS | Not ready for Inspection | Contractor cancelled. | |
| 11/07/2019 | BUILDING - PROGRESS | Not ready for Inspection | Contractor cancelled. | |
| 11/06/2019 | BUILDING - PROGRESS | Partial Approval | Exterior sheathing on North portion of building. | |
| 11/04/2019 | BUILDING - PROGRESS | Partial Approval | ||
| 11/01/2019 | BUILDING - PROGRESS | Partial Approval | Level #2; Rooms 203, 204; OK to tape progress areas. | |
| 10/31/2019 | BUILDING - PROGRESS | Partial Approval | ||
| 10/30/2019 | BUILDING - PROGRESS | Partial Approval | ||
| 10/29/2019 | BUILDING - PROGRESS | Partial Approval | Information only. | |
| 10/28/2019 | BUILDING - PROGRESS | Partial Approval | Penthouse exterior sheathing, ok to roof penthouse. | |
| 10/25/2019 | BUILDING - PROGRESS | Partial Approval | Drywall 2nd layer rooms 214, 217. | |
| 10/24/2019 | BUILDING - PROGRESS | Not ready for Inspection | Nothing ready. | |
| 10/23/2019 | BUILDING - PROGRESS | Partial Approval | (01035); shear walls in units #212 and 218. Ok to cover walls. | |
| 10/18/2019 | BUILDING - PROGRESS | Partial Approval | (01025). Roof level parapet walls; mid courtyard to Northwest area. Ok to waterproof progress areas. | |
| 10/17/2019 | BUILDING - PROGRESS | Partial Approval | ||
| 10/16/2019 | BUILDING - PROGRESS | Partial Approval | ||
| 10/15/2019 | BUILDING - PROGRESS | Partial Approval | Information only. | |
| 10/14/2019 | BUILDING - PROGRESS | Partial Approval | Information only. | |
| 10/11/2019 | BUILDING - PROGRESS | Not ready for Inspection | Level #6 parapet walls. Contractor cancelled. | |
| 10/10/2019 | BUILDING - PROGRESS | Partial Approval | South exterior walls at level #6 and parapet walls. Ok to waterproof progress areas | |
| 10/09/2019 | BUILDING - PROGRESS | Partial Approval | Mechanical, Electrical, Plumbing on Level #5; Section B: rooms and corridors. Ok to insulate and cover walls. | |
| 10/08/2019 | BUILDING - PROGRESS | Partial Approval | Mechanical, Electrical and Plumbing above ceiling in rooms and corridors in Section A, Level #5, | |
| 10/04/2019 | BUILDING - PROGRESS | Not ready for Inspection | Level #5; Sections A & B (MEP’s); will reschedule for 8 October. | |
| 10/03/2019 | BUILDING - PROGRESS | Not ready for Inspection | Contractor cancelled. | |
| 10/02/2019 | BUILDING - PROGRESS | Partial Approval | (Roof Nailing). Level #6; Section A, Roof deck and parapet walls. Ok to set roof drains and crickets. | |
| 10/01/2019 | BUILDING - PROGRESS | Partial Approval | Level #5; Rooms in Sections A & B. | |
| 09/30/2019 | BUILDING - PROGRESS | Not ready for Inspection | Contractor cancelled, no inspections for today. | |
| 09/27/2019 | BUILDING - PROGRESS | Partial Approval | Level #5; Section B, ATS hold downs in place. | |
| 09/26/2019 | BUILDING - PROGRESS | Partial Approval | Above ceilings in Level #4 corridors of Section A & B. Ok to cover progress areas. |
|
| 09/25/2019 | BUILDING - PROGRESS | Cancelled | Inspection done on 9/24/19 by Jim | |
| 09/24/2019 | BUILDING - PROGRESS | Partial Approval | Mechanical, Electrical, Plumbing above ceiling on Level #4; sections A & B. Ok to cover when all areas dry out from rain. | |
| 09/23/2019 | BUILDING - PROGRESS | Partial Approval | South exterior walls and court yard exterior walls all at Levels #4 & 5. Ok to waterproof progress areas. | |
| 04/11/2019 | BUILDING - PROGRESS | Partial Approval | Prototype 2 hour rated wall for stairwells and elevator shafts. Ok to continue use | |
| 03/19/2019 | BUILDING - PROGRESS | Not ready for Inspection | No inspections for today as per contractor | |
| 03/08/2019 | BUILDING - PROGRESS | Partial Approval | Post Tension Cabling system information |